Holding cost is $2.50/unit/week (period)
setup cost: $175
Lead time 1 week
beginning inventory 50
stockout cost=$10
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross Requirements | 30 | 20 | 40 | 10 | 40 | 60 | 20 | 80 | 10 | 90 | 70 | 10 |
1. Develop a lot for lot solution and calculate total relevant costs for the data in the above tables.
2. Develop a EOQ solution and calculate total relevant costs for the data in the above tables.
3. Develop a POQ solution and calculate total relevant costs for the data in the above tables.
4. Using the data above which is the best technique and why?