Hotchkiss Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two producing departments,
Question:
Hotchkiss Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two producing departments, P1 and P2. The Maintenance Department costs of $90,000 are allocated on the basis of standard service hours used. The Personnel Department costs of $9,000 are allocated on the basis of number of employees. The direct costs of Departments P1 and P2 are $36,000 and $60,000, respectively.
Data on standard service hours and number of employees are as follows:
Maint. | Person. | Dept. | Dept. | |
Standard service hours used | 400 | 200 | 1,200 | 600 |
Number of employees | 20 | 40 | 180 | 180 |
Direct labor hours | 200 | 200 | 1,000 | 1,000 |
What are the total overhead costs associated with P2 after allocating the Maintenance and Personnel Departments using the direct method?
a.$94,500
b.$48,000
c.$90,000
d.$99,000
Diane's Pottery Manufacturing Company has two support departments, Maintenance Department and Personnel Department, and two producing departments, X and Y. The Maintenance Department costs of $30,000 are allocated on the basis of standard service hours used. The Personnel Department costs of $4,500 are allocated on the basis of number of employees. The direct costs of Departments X and Y are $9,000 and $15,000, respectively.
Data on standard service hours and number of employees are as follows:
Maint. | Person. | Dept. | Dept. | |
Dept. | Dept. | X | Y | |
Standard service hours used | 100 | 75 | 600 | 300 |
Number of employees | 50 | 100 | 150 | 150 |
Direct labor hours | 125 | 125 | 500 | 250 |
What are the total overhead costs associated with Department Y after allocating the Maintenance and Personnel Departments using the direct method?
a.$27,250
b.$15,000
c.$25,000
d.$17,250
Cornerstones of Cost Management
ISBN: 978-1285751788
3rd edition
Authors: Don R. Hansen, Maryanne M. Mowen