If Earned Value (EV)=750, Actual Cost (AC)=720, Planned Value (PV)=725, CPI=1.04167 and SV=25 How big is the
Fantastic news! We've Found the answer you've been seeking!
Question:
If Earned Value (EV)=750, Actual Cost (AC)=720, Planned Value (PV)=725, CPI=1.04167 and SV=25 How big is the Cost Variance?