If the predecessor in a start-to-start dependency ends very late, what problem arises? Select an answer: The
Fantastic news! We've Found the answer you've been seeking!
Question:
If the predecessor in a start-to-start dependency ends very late, what problem arises?
Select an answer:
- The predecessor's late finish doesn't cause a problem.
- The successor finish date is delayed based on the predecessor's finish date.
- The successor may be scheduled to finish before the predecessor.
- The successor and the rest of the critical path are delayed, which delays the project finish date.