If variable costs for producing 1 unit are 4.5 EUR, that for the production we need to
Fantastic news! We've Found the answer you've been seeking!
Question:
If variable costs for producing 1 unit are 4.5 EUR, that for the production we need to lease a machinery for 3000 EUR per year, if the production exceeds 1000 units we have to pay workers additional 3000 EUR.
We have one demand for 1500 units for a price of 10 EUR per unit. Should we launch the product? how should we do the calculation?