Iglesias, Inc. completed Job 12 on November 30. The details of Job 12 are given below:
Direct labor cost | $810 |
Direct Material Cost | $1,200 |
machine hours | 10 hours |
Direct labor hours | 22 hours |
Default Overhead Allocation Rate | $80 per machine hour |
What is the total cost of job 12?