Imagine that the team planned to complete 30 story points in an iteration, but only completed 25.
Fantastic news! We've Found the answer you've been seeking!
Question:
Imagine that the team planned to complete 30 story points in an iteration, but only completed 25. Calculate the SPI .
The earned value to date is $2.2M and the actual costs to date is $2.8M, Calculate the CPI.
Now inform how the project is going?