In 2017, Chik-Fil-A signed a contract valued at $900K. It was estimated that $650K would be required
Fantastic news! We've Found the answer you've been seeking!
Question:
In 2017, Chik-Fil-A signed a contract valued at $900K. It was estimated that $650K would be required to complete the work requested. In 2017, a total of $100K in costs had been accumulated. In 2018, the area in which the work was performed received an unexpected ice storm that knocked out power for two weeks. This caused the total estimated costs to complete the project to increase to $1M due to contingencies placed within the contract. An additional $400K costs was accumulated during 2018.
Prepare the journal entries required in 2017 and 2018.
Posted Date: