In October, Pine Company reports 20,300 actual direct labor hours, and it incurs $125,200 of manufacturing overhead
Fantastic news! We've Found the answer you've been seeking!
Question:
In October, Pine Company reports 20,300 actual direct labor hours, and it incurs $125,200 of manufacturing overhead costs. Standard hours allowed for the work done is 24,400 hours. The predetermined overhead rate is $4.88 per direct labor hour. Compute the total overhead variance.