Jane has a fence to complete in 4 weeks. The fence will have six sections and she
Fantastic news! We've Found the answer you've been seeking!
Question:
- Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section.
- Her plan was to complete 2 sections in week one.
- You, as the PM, check the financials at the end of week one and you see that Jane has spent $1800 and has completed 1 section.
- How is Jane doing on this project as determined by Earned Value analysis?
Calculate the following:
- PV =?
- AC =?
- EV =?
- CV =?
- SV =?
- CPI =?
- SPI =?
- BAC =?
- EAC =?
- VAC =?
- ETC =?
- TCPI =?
Related Book For
Engineering Economy
ISBN: 978-0132554909
15th edition
Authors: William G. Sullivan, Elin M. Wicks, C. Patrick Koelling