Jenny designed her schedule for the project as shown in Table 4. Answer the following questions, Q1,
Question:
Jenny designed her schedule for the project as shown in Table 4. Answer the following questions, Q1, and Q2:.
Q1: Create the Gantt chart for Jenny based on Table 4. The origin of the time axis should be labeled as 3/1/2020
Q2: To ensure everything is correct, you review Jenny's schedule for any dates in Table 4 that appear to be infeasible. Since Jenny already announced the finish date of the project based on her schedule, you would try not to change this finish date.
That is, if you don't see any issue with Jenny's schedule after your review, there is no need to change anything. Otherwise, you will need to reschedule the project. In this case, you will make the finish date of the project as close to Jenny's as possible.
So, what is the finish date of the project after your review?
Problem 2 The manager, Jenny provided you with the information of the expected availability of resources (e.g. funds, workers, supplies, approval of permits) for the jobs of another similar project to Problem 1 (a renovation rather than construction). Clearly, a job cannot start processing until after the resources needed are available. With the above understanding, the earliest dates for each job to start at are listed in Table 3. Jenny designed her schedule for the project as shown in Table 4. Answer the following questions, Q1, and Q2:. Q1: Create the Gantt chart for Jenny based on Table 4. The origin of the time axis should be labeled as 3/1/2020. Table 3 Immediate Time needed Earliest date Job label Job description predecessor(s) (days) to start at A Select staff members 12 3/15/20 B Survey 9 3/16/20 Select equipment A 10 4/6/20 D Prepare final plan B 10 3/26/20 E Bring utilities to site B 24 4/1/20 F Interview applicants A 10 3/26/20 G Purchase/deliver equipment C 35 4/9/20 H Renovation D 40 4/5/20 Update infomation system A 15 3/26/20 J Install equipment E, G, H 4 5/15/20 K Train new staff F, I, J 6 5/23/20 Table 4 - Jenny's schedule Job label Job description Start date End date A Select staff members 3/15/20 B Survey 3/16/20 3/27/20 3/25/20 Select equipment 4/6/20 4/16/20 D Prepare final plan 3/26/20 4/5/20 E Bring utilities to site 4/1/20 4/25/20 F Interview applicants 3/28/20 4/7/20 G Purchase/deliver equipment 4/11/20 5/16/20 H Renovation 4/5/20 5/15/20 Update infomation system 3/30/20 4/14/20 J Install equipment 5/16/20 5/20/20 K Train new staff 5/22/20 5/28/20 Q2: To ensure everything is correct, you review Jenny's schedule for any dates in Table 4 that appear to be infeasible. Since Jenny already announced the finish date of the project based on her schedule, you would try not to change this finish date. That is, if you don't see any issue with Jenny's schedule after your review, there is no need to change anything. Otherwise, you will need to reschedule the project. In this case, you will make the finish date of the project as close to Jenny's as possible. So, what is the finish date of the project after your review? mm/dd/yyyy Show your schedule including start and end dates for each job, IF you change Jenny's schedule. Problem 2 The manager, Jenny provided you with the information of the expected availability of resources (e.g. funds, workers, supplies, approval of permits) for the jobs of another similar project to Problem 1 (a renovation rather than construction). Clearly, a job cannot start processing until after the resources needed are available. With the above understanding, the earliest dates for each job to start at are listed in Table 3. Jenny designed her schedule for the project as shown in Table 4. Answer the following questions, Q1, and Q2:. Q1: Create the Gantt chart for Jenny based on Table 4. The origin of the time axis should be labeled as 3/1/2020. Table 3 Immediate Time needed Earliest date Job label Job description predecessor(s) (days) to start at A Select staff members 12 3/15/20 B Survey 9 3/16/20 Select equipment A 10 4/6/20 D Prepare final plan B 10 3/26/20 E Bring utilities to site B 24 4/1/20 F Interview applicants A 10 3/26/20 G Purchase/deliver equipment C 35 4/9/20 H Renovation D 40 4/5/20 Update infomation system A 15 3/26/20 J Install equipment E, G, H 4 5/15/20 K Train new staff F, I, J 6 5/23/20 Table 4 - Jenny's schedule Job label Job description Start date End date A Select staff members 3/15/20 B Survey 3/16/20 3/27/20 3/25/20 Select equipment 4/6/20 4/16/20 D Prepare final plan 3/26/20 4/5/20 E Bring utilities to site 4/1/20 4/25/20 F Interview applicants 3/28/20 4/7/20 G Purchase/deliver equipment 4/11/20 5/16/20 H Renovation 4/5/20 5/15/20 Update infomation system 3/30/20 4/14/20 J Install equipment 5/16/20 5/20/20 K Train new staff 5/22/20 5/28/20 Q2: To ensure everything is correct, you review Jenny's schedule for any dates in Table 4 that appear to be infeasible. Since Jenny already announced the finish date of the project based on her schedule, you would try not to change this finish date. That is, if you don't see any issue with Jenny's schedule after your review, there is no need to change anything. Otherwise, you will need to reschedule the project. In this case, you will make the finish date of the project as close to Jenny's as possible. So, what is the finish date of the project after your review? mm/dd/yyyy Show your schedule including start and end dates for each job, IF you change Jenny's schedule.
Expert Answer:
Students also viewed these general management questions
-
What is the primary objective of investing? What aspect to an investment other than potential gains must be considered?
-
Jim Murray and Phyllis Lowe received a total of $61,500 from a deceased relative's estate. They decided to put $12,300 in a trust for their nephew and divide the remainder. Phyllis received 2/3 of...
-
Question 8 [6 points] Acme Masonary's business is suffering, so they are offering multiple discounts on their services. The following appears in their catalog. Enter the two missing pieces of...
-
On July 7, Splish Ltd. purchased 1,100 common shares in a privately-owned company named TWR Ltd. As the TWR shares were not traded on any stock exchange, Splish elected to account for the investment...
-
Prove that the number N of radioactive nuclei remaining in a sample after an integer number (n) of half-lives has elapsed is N No/2n = (1/2)n No. Here No stands for the initial number of nuclei.
-
Assume that Midway Cycles bought and sold a line of mountain bikes during May as follows: Midway Cycles uses the perpetual inventory system. Requirements 1. Compute the cost of ending inventory under...
-
Steel Slitting Company divides 24 " widths of rolled sheet steel into 2" and 4" widths. The 24 " widths are delivered to Steel Slitting Company by its customers and the new widths are picked up by...
-
You have been assigned to the audit team for B.B. JAMS Ltd., one of your significant clients. Below is the income statement prepared by the company's accountant for the December 31, 2012 year end....
-
(a) Find the five-number summary, and (b) draw a box-and-whisker plot of the data. 2 8 8 5 1 9 8 7 9 6 9 4 1 6 1 9 8 7 7 9 (a) Min=1 (Simplify your answer.) Q(Simplify your answer. Do not round.)
-
Ariffin had a total of 40 goats and cows in his farm. After selling 29 of them, the ratio of the number of goats sold to the number of goats left was 4: 1. The ratio of the number of cows sold to the...
-
In implementing supply chain strategy, a firm must minimize its total cost without compromising the needs of what group of people?
-
What is the difference between a hidden action and a hidden characteristic?
-
What are the five stages of constructing a prices index?
-
A square loop of wire has a perimeter of \(60 \mathrm{~cm}\) and is oriented such that two of its parallel sides form a \(30^{\circ}\) angle with the horizontal. A uniform horizontal magnetic field...
-
Why does the existence of asymmetric information mean that economic decisions do not conform to the assumptions of the standard economic model?
-
0.1012 M H2SO4 in 10.00 mL of solution requires 23.31 mL of NaOH for neutralization. What is the molarity of the NaOH?
-
1A. If the researcher is concerned about the number of variables, the nature of the analysis, and completion rates, then, he/she is at which stage of the sampling design process (Figure 11.1 in the...
-
Assemblit, Inc., is a medium-sized parts manufacturing company based in London with distribution outlets in the major cities throughout Great Britain. It has a mainframe computer in its London...
-
For the following steps in a security program, what is the most likely sequence in which they will be conducted? I Controls identification II Exposures analysis III Assets valuation IV Threats...
-
Briefly define what is meant by a security program. What are the eight major steps that must be undertaken during the conduct of a security program?
Study smarter with the SolutionInn App