MountainHighhas selected a capital structure D/A = 0.75. Once the firm selects its target capital structure it
Question:
MountainHigh has selected a capital structure D/A = 0.75. Once the firm selects its target capital structure it envisions two possible scenarios for its operations: Feast or Famine. The Feast scenario has a 50 percent probability of occurring and forecast EBIT in this state is $60,000. The Famine state has a 50 percent chance of occurring and the EBIT is expected to be $20,000. Further, the debt cost will be 12 percent. The firm will have $400,000 in total assets, it will face a 40 percent marginal tax rate, and the book value of equity per share under either scenario is $10.00 per share.
What is the coefficient of variation of expected EPS under the capital structure plan?
a. | 1.18 | |
b. | 3.76 | |
c. | 5.00 | |
d. | 2.88 | |
e. | 2.45 |
Financial management theory and practice
ISBN: 978-1439078099
13th edition
Authors: Eugene F. Brigham and Michael C. Ehrhardt