Need to calculate payback period for each project Project A Year 0 - $-8,000,000 Year 1 -
Fantastic news! We've Found the answer you've been seeking!
Question:
Need to calculate payback period for each project
Project A
Year 0 - $-8,000,000
Year 1 - $4,000,000
Year 2 - $2,500,000
Year 3 - $2,500,000
Project B
Year 0 - $-4,250,000
Year 1 - $1,500,000
Year 2 - $1,500,000
Year 3 - $1,500,000
Year 4 - $1,000,000
Project C
Year 0 - $-7,800,000
Year 1 - $1,500,000
Year 2 - $2,000,000
Year 3 - $2,000,000
Year 4 - $2,000,000
Year 5 - $2,000,000
Year 6 - $2,000,000
Year 7 - $1,500,000
Group D
Year 0 - $-5,757,000
Year 1 - $1,500,000
Year 2 - $1,500,000
Year 3 - $1,500,000
Year 4 - $1,500,000
Year 5 - $1,000,000
Year 6 - $1,000,000
Year 7 - $1,000,000
Year 8 - $500,000