Provide solutions for the issues mentioned in the case study. Case Study Overview: New Energy, Inc. is
Fantastic news! We've Found the answer you've been seeking!
Question:
Provide solutions for the issues mentioned in the case study.
Transcribed Image Text:
Case Study Overview: New Energy, Inc. is a fast-growing supplier of "green" energy solutions, including wind turbines, solar technology, etc. Their growing sales force and varying sales commission plans prompted the need for a centralized and automated commission system to replace their spreadsheet- intensive procedures. Project: Don is the head of Accounting and approved the project plan developed by the assigned project manager, Mary. Their preliminary research showed that a software package was the most cost- effective solution. Mary's scope statement included these project objectives: o Research and produce a list of the three packages that best fit the company's need. o Facilitate a decision for the best package to obtain o Procure the package. o Install the package. Progress: It took months to research and find the three packages. Selecting the package was contentious. The Sales department wanted a web-based solution, which the VP of sales, Chris, said would be easiest for the salespeople to use. Accounting wanted a product that had tighter security and was easier to customize. Since the system was being paid for with Accounting's budget, Don prevailed. Issue 1: Once the software contract was signed, Don became busy and largely left the installation to Mary and the technical team. Don wanted the project completed by a fixed date, and Mary felt pressured to get installation done without much requirements analysis, especially given she had only one systems analyst, Bob, on the project. Issue 2: Bob focused his time on converting the spreadsheet data to the new system, and on customizing the many new user interfaces available. He conducted extensive interviews of key staff to learn their needs for the interfaces. As Bob was interviewing, Chris requested that the most common sales interface be duplicated as a web page, and Bob agreed because it was easy. While they were at it, Bob showed Chris a nifty Flash component for the page, which Chris loved, and it was added as a requirement. Issue 3: During the package installation, Sales announced the addition of a new product line with an entirely different commission structure. Don held a meeting and informed the team that the new commission plan had to be incorporated into the project and that the deadline could not slip. Issue 4: During installation, Bill, a developer, and the Accounts Payable lead, Allison, discovered that the project scope did not include changes to other systems like General Ledger (G/L). Bill said he could code something quickly and that this would save Allison's team many hours every payroll. He was ahead of schedule, so Mary agreed. Unfortunately, it took longer to code and test than Bill thought, and consequently he didn't finish testing all of the exceptions for the new commission system. The package was implemented on schedule, but with several problems due to some exceptions not working correctly. There were other problems with bad data and incorrect reports. Don was not happy. Case Study Overview: New Energy, Inc. is a fast-growing supplier of "green" energy solutions, including wind turbines, solar technology, etc. Their growing sales force and varying sales commission plans prompted the need for a centralized and automated commission system to replace their spreadsheet- intensive procedures. Project: Don is the head of Accounting and approved the project plan developed by the assigned project manager, Mary. Their preliminary research showed that a software package was the most cost- effective solution. Mary's scope statement included these project objectives: o Research and produce a list of the three packages that best fit the company's need. o Facilitate a decision for the best package to obtain o Procure the package. o Install the package. Progress: It took months to research and find the three packages. Selecting the package was contentious. The Sales department wanted a web-based solution, which the VP of sales, Chris, said would be easiest for the salespeople to use. Accounting wanted a product that had tighter security and was easier to customize. Since the system was being paid for with Accounting's budget, Don prevailed. Issue 1: Once the software contract was signed, Don became busy and largely left the installation to Mary and the technical team. Don wanted the project completed by a fixed date, and Mary felt pressured to get installation done without much requirements analysis, especially given she had only one systems analyst, Bob, on the project. Issue 2: Bob focused his time on converting the spreadsheet data to the new system, and on customizing the many new user interfaces available. He conducted extensive interviews of key staff to learn their needs for the interfaces. As Bob was interviewing, Chris requested that the most common sales interface be duplicated as a web page, and Bob agreed because it was easy. While they were at it, Bob showed Chris a nifty Flash component for the page, which Chris loved, and it was added as a requirement. Issue 3: During the package installation, Sales announced the addition of a new product line with an entirely different commission structure. Don held a meeting and informed the team that the new commission plan had to be incorporated into the project and that the deadline could not slip. Issue 4: During installation, Bill, a developer, and the Accounts Payable lead, Allison, discovered that the project scope did not include changes to other systems like General Ledger (G/L). Bill said he could code something quickly and that this would save Allison's team many hours every payroll. He was ahead of schedule, so Mary agreed. Unfortunately, it took longer to code and test than Bill thought, and consequently he didn't finish testing all of the exceptions for the new commission system. The package was implemented on schedule, but with several problems due to some exceptions not working correctly. There were other problems with bad data and incorrect reports. Don was not happy.
Expert Answer:
Answer rating: 100% (QA)
The software development that was being implemented by the company faced some challenges that could ... View the full answer
Related Book For
Managing Business Ethics Making Ethical Decisions
ISBN: 9781506388595
1st Edition
Authors: Alfred A. Marcus, Timothy J. Hargrave
Posted Date:
Students also viewed these general management questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
List all paths from A to H. Which paths have the lowest weight? Which path has shortest length? Is the graph connected (strongly or weakly)? 3 12 15 18 F 10 5 19 B' H 10 6 5 3 22 E G
-
Choose the specific factor (for example, culture, family, occupation, attitudes) that most accounts for the blue/pink toy aisle phenomenon. Explain the challenges faced by Goldie-Blox in attempting...
-
If, in problem 16.5, the process is improved so the standard deviation is 0.0035, is the process capable now? In Problem The specification for the diameter of a hole is 0.80 inch 0.020 inch. The...
-
Using rules of thumb for a \(200 \mathrm{~m}^{2}\) floor area Denver residence, determine (a) the auxiliary heating energy required, (b) the solar projected area, (c) the concrete storage mass needed...
-
Buffett sent a violin to Strotokowsky by International Parcel Service (IPS), a common carrier. Buffett declared the value of the parcel at $500 on the pick-up receipt given him by the IPS driver. The...
-
Analyzing Central Tendency of Data, We all have heard or read mainstream statistics used in many contexts. These are statistics such as mean, median, minimum, maximum, correlation etc. Alone, they...
-
1. Assuming Anson decided to charge barrel costs (but not warehousing and aging costs) to inventory, what 2012 income statement and balance sheet items would change, and what would the new amounts...
-
1) Estimate the probability of finding an electron in a hydrogen atom anywhere within onemeter of the proton. 2) Calculate the probability of finding an electron in a hydrogen atom anywhere within...
-
Refer to the monthly stock price of OO C0mpany, MM C0mpany and VV C0mpany for the last 3 years. For each stock, Calculate: a) Average yearly rate of return b) Standard deviation c) Beta Question...
-
Analyze output. What do the measures tell you? Is your data skewed? Does it exhibit kurtosis? What is the interquartile range? What insights about the data you have chosen do you derive from this...
-
Calculate current market price using NPV 5 Current Dividend, DO 6 Stage 1 growth rate, gl 7 Length of stage 1 (in yrs) 8 Stage 2 growth rate, g2 9 Req. rate of return 10 11 Outputs: 13 14 15 16 17 18...
-
a) How many different Boolean functions of N variables are there? b) A three-input OR-AND-INVERT (OAI) gate is shown below. Complete the truth table for it. Doar c) Write a truth table for the...
-
Design a 10 GHz oscillator using a common gate GaAs FET. The S parameters of the transistor at 10 GHz are given below $110.85-36 S12=0.22-36 S21 = 0.53.296 $22=1.1252171 Use 500 microstrip lines to...
-
8. Suppose that on January 1, 20X1, Hazelnut Group acquired 25% shares of Cashew Nut Corporation for $17,000. All other information is the same as above. During 20X1, Cashew Nut Corporation has net...
-
Activator rod AB exerts on crank BCD a force P directed along line AB. Knowing that P must have a 100-N component perpendicular to arm BC of the crank, determine (a) The magnitude of the force P, (b)...
-
ACI is a leading supplier of components for the telecommunications industry. It sells components to companies like Alcatel, Northern Telecom, and Ericsson, who put the components into the equipment...
-
You are on the management team of a rapidly growing apparel company that had $780 million in sales last year and is projecting an additional $150 million in sales this year. You have been invited to...
-
Pithos Internet Company is known for its innovative software products. The secret to Pithoss success is in large part its ability to create a climate in which its smart and ambitious employees are...
-
Find the response of a simple pendulum numerically by solving the exact equation: \[\ddot{\theta}+\frac{g}{l} \sin \theta=0\] with \(\frac{g}{l}=0.01\) and plot the response, \(\theta(t)\), for \(0...
-
Using MATLAB function ode23, solve the differential equation \(5 \ddot{x}+4 \dot{x}+3 x=6 \sin t\) with \(x(0)=\dot{x}(0)=0\).
-
Find the response of a simple pendulum numerically by solving the nonlinear equation: \[\ddot{\theta}+\frac{g}{l}\left(\theta-\frac{\theta^{3}}{6} ight)=0\] with \(\frac{g}{l}=0.01\) and plot the...
Study smarter with the SolutionInn App