Given the schedule in the following table-for a software development project: (12 points) (SO 02) Activity...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Given the schedule in the following table-for a software development project: (12 points) (SO 02) Activity Immediate Duration Early Start Early Finish Late Start Late Finish Free Total Slack Slack predecessor activities Date Date Date Date A 01/02/2020 06/02/2020 01/02/2020 07/02/2020 B А, В 8 D B E B F D 9. G C, E б H H A. Draw the Gantt chart of the specified project in the table above? (2 points) B. Complete filling the table if the start date of the project is on Saturday 01/02/2020 (assume no vacations) and calculate the needed dates and values: (10 points) Attach your answer in handwritten format with the permitted types of files. 6. Given the schedule in the following table-for a software development project: (12 points) (SO 02) Activity Immediate Duration Early Start Early Finish Late Start Late Finish Free Total Slack Slack predecessor activities Date Date Date Date A 01/02/2020 06/02/2020 01/02/2020 07/02/2020 B А, В 8 D B E B F D 9. G C, E б H H A. Draw the Gantt chart of the specified project in the table above? (2 points) B. Complete filling the table if the start date of the project is on Saturday 01/02/2020 (assume no vacations) and calculate the needed dates and values: (10 points) Attach your answer in handwritten format with the permitted types of files. 6.
Expert Answer:
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Posted Date:
Students also viewed these computer network questions
-
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and...
-
Draw a Gantt chart of your solution to Problem 14. Evaluate the idle time, if any, for these two resources-exterior and interior cleaning capability. The schedules are shown on the following Gantt...
-
Complete the following table for a queuing simulation. Customer Arrival ServiceStart End Waiting Server Time l ime Time Time Time Idle Time 0.6 2.2 3.3 1.0 0.8 4.2 0.8 2.9 4.9 6.6 9.4 10.6 11.1 13.3...
-
Governmental Funds Statement of Revenues Expenditures and Changes in Fund Balance. You have recently started working as the controller for a small county. The county is preparing its financial...
-
The math and reading achievement scores from the National Assessment of Educational Progress for selected states are listed below. Construct a back-to back stem and leaf plot with the data and...
-
Italian Leather Goods Inc. began 2020 with an inventory of 50,000 units that cost \(\$ 1,500,000\). During the year, the store purchased merchandise on account as follows: Cash payments on account...
-
The accounting records for ADR, Inc., reflected the following amounts at the end of August 2010: Prepare the ADR, Inc., classified balance sheet at August 31,2010. Use the report format. Cash......
-
The Delmar Beverage Co. produces a premium root beer that is sold throughout its chain of restaurants in the Midwest. The company is currently producing 4,000 gallons of root beer per day, which...
-
(a) Give a list of the common applications of planetary gear trains. Describe the working of the dif- ferential mechanism of a motor car. (b) In the planetary gear train shown in Fig.15.37, gear 1...
-
Alfonso Inc. acquired 100 percent of the voting shares of BelAire Company on January 1, 2020. In exchange, Alfonso paid $198,000 in cash and issued 100,000 shares of its own $1 par value common...
-
Hal Wipley is the owner of Samantha Company and has hired Jenna Walters to value his firm as he is contemplating retirement. Walters made the following estimates: High-Growth Stage Stable-Growth...
-
Explain why protecting a foundation from large forces generated by a machine is similar to protecting a body from large accelerations by its base.
-
Steam enters a turbine at \(700 \mathrm{kPa}, 250^{\circ} \mathrm{C}\) and exhausts at \(15 \mathrm{kPa}\). The efficiency of the turbine is 0.8. Calculate (a) the power output per \(\mathrm{kg}\) of...
-
What is percentage isolation?
-
Explain why vibration isolation is difficult at low speeds.
-
How is frequency response determined for the motion of a machine on a moveable foundation?
-
How do you validate the integrity of data stored in distributed databases and data lakes, including the implementation of distributed consensus protocols, distributed transaction processing, and data...
-
As indicated by mutual fund flows, investors tend to beat the market seek safety invest in last year's winner invest in last years loser
-
What are the pros and cons of the head of a Project Management Office reporting to senior management? To departmental management?
-
Describe the concept critical chain in your own words.
-
Why is it important to use outside auditors rather than inside auditors who would be more familiar with the company and the project?
-
Should the instruction following the TEST instruction be interruptible? If so, what must the implicit BRANCH instruction (interrupt) do?
-
It seems that there are far fewer commercial implementations of SIMD, MIMD, and MISD architectures than there were just 10 years ago. This is probably due to a variety of factors, including high...
-
GCP, Inc., has contracted you to analyze and develop commercial off-the-shelf (COTS) processors to be phased into their existing product lines. Your objective is to select four popular commercial...
Study smarter with the SolutionInn App