QUESTION TWO [25] Khoza's Manufacturing makes calculators for the local retail markets. They have received an order
No answer yet for this question.
Ask a Tutor
Question:
QUESTION TWO [25]
Khoza's Manufacturing makes calculators for the local retail markets. They have received an order of 4500 calculators. The order is due for delivery on week 5. Each calculator consists of a cover, process chip and keypad. The cover is made up of a display unit and 2 battery housings. The cover is made by the firm and takes 2 weeks to produce. The process chip and keypads are ordered and the lead time is three weeks. Final assembly requires 1 weeks. There are scheduled receipts as follows:
Component | Week No. | Batch Size | ||||
1 | 2 | 3 | ||||
Process Chip | 450 | 900 | 450 | |||
Keypad | 480 | 360 | 120 |
2.1 Construct a Bill of Material (BOM) for the above. (5)
2.2 Draw an Assembly Time Chart. (5)
2.3 Develop a net requirement plan for Khoza's Manufacturing. (15)