RASHING DATA (The normal time is the calculated t time calculated from question 1 data) Please determine
Question:
RASHING DATA (The normal time is the calculated t time calculated from question 1 data)
Please determine the following: (Crash the Project to Maximum feasible)
a) Crash Cost per day for each node(CCPD) (10 Marks)
b) Amount to crash each node (days) (Crash By) in column (CB)(15 Marks)
c) Crash Costby node crashed and theTotal cost for the Project after crashing(15 Marks)
d) What is thenew estimated timefor the crashed project.Is there a new Critical Path if yes what is it?(5 Marks)
e) If theafter Crash Budgetwas set to$98000and the time frame to22days after crashing to the max can the project becompleted on time? On budget? (Indicate the amount the project is over or under time and budget) MUST state amount over / under in days and cost to get any marks.(5 Marks)
(Question Value 50 Marks)