Refer to the network below Baseline schedule PS Activity 0,6 J 0,6 0,2 B 2 1,3...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Refer to the network below Baseline schedule PS Activity 0,6 J 0,6 0,2 B 2 1,3 0,9 C g ABCDEFGH 1629475108 11, 20 Duration 32 IPA A. B B D D. E 6,10 C. F. G A 6, 10 15, 20 10, 20 28, 30 hg0 m 10 10, 20 28, 30 2,9 E 7 3,10 CE0006210 10 20 ES EF 6 2 9 10 9 15 20 28 C, G 20 23 HT 28 10, 15 F 30 LS 1 TO- 1635 10 20 |U6320 10 10 20 20 28 28 30 -101500 1500 25 28 11 20, 28 LF H 20, 28 20, 23 1 3 25, 28 TF 1 po FF FO 0 5o Fifteen days after the start of the project, the following information is received. - Activity A Completed 2 days later than planned - Activity B Completed on time - Activity C Started; 4 days left - Activity D Completed; took 5 days to finish - Activity E Completed - Activity F Canceled - Activity G Started 3 days late; project manager hopes to cut 1 day of its duration - Activity K Added: Duration = 4 days. IPA - C - Activity LAdded: Duration=3 days. IPA - K, G - Activity | Adjusted: IPA - L Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any. Refer to the network below Baseline schedule PS Activity 0,6 J 0,6 0,2 B 2 1,3 0,9 C g ABCDEFGH 1629475108 11, 20 Duration 32 IPA A. B B D D. E 6,10 C. F. G A 6, 10 15, 20 10, 20 28, 30 hg0 m 10 10, 20 28, 30 2,9 E 7 3,10 CE0006210 10 20 ES EF 6 2 9 10 9 15 20 28 C, G 20 23 HT 28 10, 15 F 30 LS 1 TO- 1635 10 20 |U6320 10 10 20 20 28 28 30 -101500 1500 25 28 11 20, 28 LF H 20, 28 20, 23 1 3 25, 28 TF 1 po FF FO 0 5o Fifteen days after the start of the project, the following information is received. - Activity A Completed 2 days later than planned - Activity B Completed on time - Activity C Started; 4 days left - Activity D Completed; took 5 days to finish - Activity E Completed - Activity F Canceled - Activity G Started 3 days late; project manager hopes to cut 1 day of its duration - Activity K Added: Duration = 4 days. IPA - C - Activity LAdded: Duration=3 days. IPA - K, G - Activity | Adjusted: IPA - L Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any.
Expert Answer:
Answer rating: 100% (QA)
Given the updates to the project we need to adjust the network diagram and recalculate the project completion date Since I cannot physically draw the ... View the full answer
Related Book For
Posted Date:
Students also viewed these general management questions
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-6. On December 12, Irene purchased the building where her store is located. She paid...
-
Think about the impact that e-commerce and more flexible networks of organisations has had on the way international business is conducted. How has it created new complexities in the relationships...
-
If there is uncertainty about some monetary outcome and you are concerned about return and risk, then all you need to see are the mean and standard deviation. The entire distribution provides no...
-
The income statement for Weatherford International Inc.?s year ended December 31, 2020, was prepared by an inexperienced bookkeeper. As the new accountant, your immediate priority is to correct the...
-
When sampling for attributes, which of the following would decrease sample size? Choose the best answer. Risk of Assessing Control Risk Too Low a. Increase b. Decrease c. Increase d. Increase...
-
The L. Young & Sons Manufacturing Company produces two products, which have the following profit and resource requirement characteristics: Last months production schedule used 350 hours of labor in...
-
www 6. Linus Ullmark of the Boston Bruins had the best save percentage of a goalie in the 2022-2023 season. We take this to mean, loosely, that Ullmark has a 93.8% chance of making a save when a puck...
-
Cascade Company has four employees. All are paid on a monthly basis. The fiscal year of the business is June 1 to May 31. The accounts kept by Cascade include the following: .:. The following...
-
Bright World LLC (BW) distributes sunglasses to small retail stores in the Midwest part of the United States. BW does not manufacture the sunglasses, but instead buys the sunglasses from foreign...
-
= (i) Let x = In(2) and y -0.6931457. Using 5-decimal digit rounding and normalized floating-point representation, compute the sum of xy, where denotes computer arith- metic addition with 6-decimal...
-
Figure (a) shows, in cross section, two long, parallel wires carrying current and separated by distance L. The ratio i/i2 of their currents is 5.60; the directions of the currents are not indicated....
-
The following diagram shows the Gint coefficient and income share of the B40. M40 and T20 groups in Malaysia between the years 1970 and 2019. Income Share (%) 70.0 60.0 55.7 50.0 40.0 30.0 20.0 10.0...
-
2 2 points A glass of height 16.0 cm and diameter 8.00 cm is completely filled with an unknown liquid. A coin is placed in the exact center of the cup. See the figure. Light reflecting off the coin...
-
Given a Cobb-Douglas production function Q (L, K) = 10.00L0.600K0.500 where L is labor (i.e. workers) and K is capital (i.e. machinery, tools) (A) (5 Points) Please fill in the empty 7x7 matrix cells...
-
ed Maria Gomez owns and manages a consulting firm called Accel, which began operations on December 1. She asks us to assist her with some financial reporting questions. On December 31, we are...
-
Draw the major product for each of the following reactions: (a) (b) (c) 1) 9-BBN 2) H2O2, NaOH 1) Disiamylborane 2) H20, NaOH
-
Wet concrete exerts a pressure distribution along the wall of the form. Determine resultant force of this distribution and specify the height h where the bracing strut should be placed so that it...
-
Determine the normal force, shear force, and moment at points D of the two-member frame. 2 kN/m A -1.5 m D -1.5 m 1.5 m E 1.5 m O F B 1.5 kN/m
-
Determine the location (x, ) of the centroid of the sheet metal cross section. Neglect the thickness of the material and slight bends at the corners. y 2 in. 8 in. -3 in.3 in. X
-
A system with a natural frequency of \(10 \mathrm{rad} / \mathrm{s}\) has a shorter period than a system of natural frequency \(100 \mathrm{rad} / \mathrm{s}\). Indicate whether the statement...
-
The natural frequency determined directly from the differential equation of motion has units of Hertz. Indicate whether the statement presented is true or false. If true, state why. If false, rewrite...
-
A system with a damping ratio of 1.2 is overdamped. Indicate whether the statement presented is true or false. If true, state why. If false, rewrite the statement to make it true.
Study smarter with the SolutionInn App