ABC Manufacturing is developing their 2017 SOP. The sales plan is already developed, using the forecast obtained
Question:
ABC Manufacturing is developing their 2017 SOP. The sales plan is already developed, using the forecast obtained from Demand Management and is as follows: (the numbers are in 1000’s)
Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
420 | 375 | 425 | 600 | 200 | 100 | 150 | 250 | 420 | 390 | 420 | 450 |
Other problem parameters are:
Initial worker level = 500, Initial inventory = 100,000, Required ending inventory = 100,000, Cost per unit = $50, one worker can produce 600 units/month
Hiring cost = $150 per worker, Firing cost = $300 per worker, Inventory holding cost = 0.5% of item cost/month, Shortage cost = 1% of item cost/month.
1.) Develop a Chase plan
2.) Develop a Level plan
For each plan, calculate the end of month inventory (or shortage) level, monthly hiring and firing schedule and costs, monthly inventory and shortage costs, and the total cost.
3.) By trial and error, come up with a mix strategy that will have less total cost than any of the above two.