Sam Sparrow Manufacturing produces custom-built pollution control devices for medium-size steel mills. The most recent project undertaken
Fantastic news! We've Found the answer you've been seeking!
Question:
- Sam Sparrow Manufacturing produces custom-built pollution control devices for medium-size steel mills. The most recent project undertaken by Sam requires 14 different activities. (20 points)
- Sam's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table.
- What is the probability of being done in 53 days?
- What date results in a 99% probability of completion?
- Sam Sparrow Manufacturing produces custom-built pollution control devices for medium-size steel mills. The most recent project undertaken by Sam requires 14 different activities. (20 points)
- Sam's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table.
- What is the probability of being done in 53 days?
- What date results in a 99% probability of completion?
Activity | Immediate Predecessors | Optimistic Time | Most Likely Time | Pessimistic Time | |||||
A | --- | 4 | 6 | 7 | 5.83 | .5 | |||
B | --- | 1 | 2 | 3 | 2 | ||||
C | A | 6 | 6 | 6 | 6 | 0 | |||
D | A | 5 | 8 | 11 | 8 | ||||
E | B, C | 1 | 9 | 18 | 9.17 | 2.83 | |||
F | D | 2 | 3 | 6 | 3.33 | ||||
G | D | 1 | 7 | 8 | 6.17 | ||||
H | E, F | 4 | 4 | 6 | 4.33 | 0.33 | |||
I | G, H | 1 | 6 | 8 | 5.5 | 1.17 | |||
J | I | 2 | 5 | 7 | 4.83 | ||||
K | I | 8 | 9 | 11 | 9.17 | 0.5 | |||
L | J | 2 | 4 | 6 | 4 | ||||
M | K | 1 | 2 | 3 | 2 | 0.33 | |||
N | L, M | 6 | 8 | 10 | 8 | 0.67 |