Scenario and Summary Situation: Jobs A, B, and C are waiting to be started on Machine...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Scenario and Summary Situation: Jobs A, B, and C are waiting to be started on Machine Center X. When they are finished at this center, they must be moved to Machine Center Y for final processing. Machine capacity for both centers is 40 hours in a 5-day workweek or 8 hours a day. It takes 2 days to move a job from Center X to Center Y. The following information pertains to the jobs and work centers: Job A B C Machine Center Machine Center X Y (hours required) (hours required) 36 888 96 60 20 24 28 Day Due 10 17 25 Deliverables Complete a scheduling table for each scheduling technique and determine which job can be completed on time. See the Lab Steps below for directions on how to set up your chart, and then copy your table and answers into an MS Word document. LAB STEPS STEP 1: Earliest Due Date Schedule Use the data above and complete the following table using the Earliest Due Date Scheduling method. Determine which jobs will be completed on time. Copy your table and answers to an MS Word document. Job A B C Machine Center X Start Machine Center X Days Machine Machine Center X Center X Done Move Machine Center Y Start Back to Top Machine Center Y Days Machine Center Y Done Machine Center Y Due STEP 2: Critical Ratio Schedule Using the above data, complete the following table using the Critical Ratio Scheduling method. Determine which jobs will be completed on time. Copy your table and answers to an MS Word document. Job A B C Machine Center X Start Machine Center X Days Machine Center X Done Machine Center X Move Machine Center Y Start Back to Top Machine Center Y Days Machine Center Y Done Machine Center Y Due STEP 3: Final Step in Part A Submit your completed Lab in an MS Word document for grading. Please provide only one document with all responses. Submit your assignment to the Dropbox located on the silver tab at the top of this page. For instructions on how to use the Dropbox, read these step-by-step instructions or watch this Dropbox Tutorial. See the Syllabus section "Due Dates for Assignments & Exams" for due date information. Proceed to Part B: The Input/Output Report Lab Back to Top LAB OVERVIEW Part B: The Input/Output Report Lab Back to Top This week's Lab assignment consists of two parts: the Scheduling Lab and the Input/Output Report Lab. Please be certain to complete both of them. Part B: The Input/Output Report Points Description Lab Report Construction 10 Data Assessment 10 Total Scenario and Summary Planned Input Actual Input Planned Output 20 Actual Output Situation: The following table contains the input/output data at the end of Week 8 for a work center. The beginning backlog is 50 units. Week 1 60 68 65 Using data provided to you, complete a table for the Report Construction. 60 Using the data and table for the Report Construction, answer questions for the data assessment. A quality table will meet the above requirements and a quality data assessment will meet or exceed the above requirements. Week 2 Week 3 60 60 70 75 65 65 62 63 Week 4 Week 5 Week 6 Week 7 Week 8 60 60 60 60 60 70 68 60 55 65 65 63 64 65 65 65 63 55 65 60 Deliverables Use the data from the Situation Table above and complete an Input/Output Report. See the Lab Steps below for directions on how to set up your chart, and then copy your table and answers into an MS Word document. LAB STEPS STEP 1: Report Construction Use the data from the Situation Table above and use this table for your answers, and then copy your table into an MS Word document. Planned Input Actual Input Cumulative Deviation Planned Output Actual Output Cumulative Deviation Actual Backlog STEP 2: Data Assessment Back to Top Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Copy your answers to the following questions into an MS Word document: 1. What was the planned objective? 2. Was the planned objective met? 3. What recommendation(s) would you make? Back to Top Scenario and Summary Situation: Jobs A, B, and C are waiting to be started on Machine Center X. When they are finished at this center, they must be moved to Machine Center Y for final processing. Machine capacity for both centers is 40 hours in a 5-day workweek or 8 hours a day. It takes 2 days to move a job from Center X to Center Y. The following information pertains to the jobs and work centers: Job A B C Machine Center Machine Center X Y (hours required) (hours required) 36 888 96 60 20 24 28 Day Due 10 17 25 Deliverables Complete a scheduling table for each scheduling technique and determine which job can be completed on time. See the Lab Steps below for directions on how to set up your chart, and then copy your table and answers into an MS Word document. LAB STEPS STEP 1: Earliest Due Date Schedule Use the data above and complete the following table using the Earliest Due Date Scheduling method. Determine which jobs will be completed on time. Copy your table and answers to an MS Word document. Job A B C Machine Center X Start Machine Center X Days Machine Machine Center X Center X Done Move Machine Center Y Start Back to Top Machine Center Y Days Machine Center Y Done Machine Center Y Due STEP 2: Critical Ratio Schedule Using the above data, complete the following table using the Critical Ratio Scheduling method. Determine which jobs will be completed on time. Copy your table and answers to an MS Word document. Job A B C Machine Center X Start Machine Center X Days Machine Center X Done Machine Center X Move Machine Center Y Start Back to Top Machine Center Y Days Machine Center Y Done Machine Center Y Due STEP 3: Final Step in Part A Submit your completed Lab in an MS Word document for grading. Please provide only one document with all responses. Submit your assignment to the Dropbox located on the silver tab at the top of this page. For instructions on how to use the Dropbox, read these step-by-step instructions or watch this Dropbox Tutorial. See the Syllabus section "Due Dates for Assignments & Exams" for due date information. Proceed to Part B: The Input/Output Report Lab Back to Top LAB OVERVIEW Part B: The Input/Output Report Lab Back to Top This week's Lab assignment consists of two parts: the Scheduling Lab and the Input/Output Report Lab. Please be certain to complete both of them. Part B: The Input/Output Report Points Description Lab Report Construction 10 Data Assessment 10 Total Scenario and Summary Planned Input Actual Input Planned Output 20 Actual Output Situation: The following table contains the input/output data at the end of Week 8 for a work center. The beginning backlog is 50 units. Week 1 60 68 65 Using data provided to you, complete a table for the Report Construction. 60 Using the data and table for the Report Construction, answer questions for the data assessment. A quality table will meet the above requirements and a quality data assessment will meet or exceed the above requirements. Week 2 Week 3 60 60 70 75 65 65 62 63 Week 4 Week 5 Week 6 Week 7 Week 8 60 60 60 60 60 70 68 60 55 65 65 63 64 65 65 65 63 55 65 60 Deliverables Use the data from the Situation Table above and complete an Input/Output Report. See the Lab Steps below for directions on how to set up your chart, and then copy your table and answers into an MS Word document. LAB STEPS STEP 1: Report Construction Use the data from the Situation Table above and use this table for your answers, and then copy your table into an MS Word document. Planned Input Actual Input Cumulative Deviation Planned Output Actual Output Cumulative Deviation Actual Backlog STEP 2: Data Assessment Back to Top Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Copy your answers to the following questions into an MS Word document: 1. What was the planned objective? 2. Was the planned objective met? 3. What recommendation(s) would you make? Back to Top
Expert Answer:
Answer rating: 100% (QA)
Answer Explanation Answer Planned Input 60 60 60 60 60 60 60 60 Actual Input 68 70 75 70 68 60 55 55 ... View the full answer
Related Book For
Posted Date:
Students also viewed these accounting questions
-
Jobs A, B, and C are waiting to be started on Machine Center X. When they are finished at this center, they must be moved to Machine Center Y for final processing. Machine capacity for both centers...
-
Jobs A, B, and C are waiting to be started on machine center X and then be completed on machine center Y. The following information pertains to the jobs and work centers. Machine center X and machine...
-
The Production manager of the Good Time Wine Rack Company is retiring and the Managing Director is looking to replace her. You are preparing a work schedule as youare hoping to be offeredthe position...
-
Stanley, Inc. issues 15-year $1,000 bonds that pay $85 annually. The market price for the bonds is $960. Your required rate of return is 9 percent.
-
Patricia Garcia and Bernardo Lucero were in a romantic relationship. While they were seeing each other, Garcia and Lucero acquired an electronics service center, paying $ 30,000 apiece. Two years...
-
As part of a Type A reorganization, Hall Corp. transferred property with a value of \(\$ 15\) million and a basis of \(\$ 8\) million, in exchange for \(\$ 13\) million worth of stock in Gate Corp....
-
Imagine you are the CIO of a hospital in which almost no computer-based tools are used. One of the hospital's goals is to support health care professionals in their daily tasks by offering up-to-date...
-
Gross Profit Method Sliver Lumber Company handles three principal lines of merchandise with these varying rates of gross profit on cost. Lumber.......................25%...
-
Today we are going to calculate the electric field of two concentric non-conducting charged cylinders (separated by a neutral insulator) of infinite length in all regions of space. We will be using...
-
Alexander Smith and his wife Allison are married and file a joint tax return for 2021. The Smiths live at 1234 Buena Vista Drive, Orlando, FL 32830. Alexander is a commuter airline pilot but took 6...
-
Symbolic convergence theory highlights the strength of storytelling in small groups. Is it possible for certain stories to reduce the morale of the group and lead to negative outcomes? Explain. The...
-
How are the test cases developed for acceptance tests?
-
What are the primary disadvantages of online documentation?
-
Examine and prepare a report on the online help system for the calculator program in Windows (or a similar one on the Mac or Unix). (You will probably be surprised at the amount of help for such a...
-
Besides Hall and Hofstede, both David Victor and Fons Trompenaars have identified a set of cultural dimensions that could be useful in information systems development. Using the Web, identify their...
-
Different views of plagiarism and collaborative learning were described as examples of differences among different cultures today. Using the Web, identify other differences that could affect the...
-
Why are employee performance appraisals conducted? In order to meet government requirements To measure employee performance and determine raises and promotions In order to identify employee...
-
Describe basic managerial approaches to implementing controls and how these are implemented.
-
Using the data in problem 7.5, determine the best process for each of the following volumes: (1) 75,000, (2) 275,000, and (3) 375,000. In problem 7.5, Meile Machine Shop, Inc., has a 1-year contract...
-
Daily high temperatures in St. Louis for the last week were as follows: 93, 94, 93, 95, 96, 88, 90 (yesterday). (a) Forecast the high temperature today, using a 3-day moving average. (b) Forecast the...
-
Klassen Toy Company, Inc., assembles two parts (parts 1 and 2): Part 1 is first processed at workstation A for 15 minutes per unit and then processed at workstation B for 10 minutes per unit. Part 2...
-
Find the fundamental natural frequency of vibration of a uniform beam of length \(l\) that is fixed at one end and simply supported at the other end. Assume the deflection shape of the beam to be...
-
Determine the fundamental frequency of a uniform fixed-fixed beam carrying a mass \(M\) at the middle by applying Rayleigh's method. Use the static deflection curve for \(W(x)\).
-
Applying Rayleigh's method, determine the fundamental frequency of a cantilever beam (fixed at \(x=l\) ) whose cross-sectional area \(A(x)\) and moment of inertia \(I(x)\) vary as \(A(x)=A_{0} x /...
Study smarter with the SolutionInn App