Schedule the following 7 jobs that requires processing on 2 machines in a flow shop to minimize
Fantastic news! We've Found the answer you've been seeking!
Question:
Schedule the following 7 jobs that requires processing on 2 machines in a flow shop to minimize the makespan. On what day will job 4 be completed?
Job | pi1 | pi2 |
J1 | 5 | 4 |
J2 | 6 | 7 |
J3 | 5 | 11 |
J4 | 3 | 8 |
J5 | 10 | 2 |
J6 | 9 | 7 |
J7 | 1 | 5 |