tab Problem #2 Crashing - has the information for the project. Answer questions A to F...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing The the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $300/day. Complete the tables and write up your narrative in the text box provided. Activity A B C D Path E F G H Predecessor Normal Time B A, C A, C B D E, F Crash Crash Cost Direct Cost Indirect Cost Total Cost Duration (Normal Time) 5 4 7 2 3 8 5 6 Normal Cost $500 $400 $700 $200 $300 $800 $500 $600 Crash Time Crash Cost 3 2 6 1 - 5 4 3 $1,500 $2,000 $1,600 $500 $2,900 $1,000 $1,800 Part D: The Plan for 18 days (complete the table below - there maybe more columns/rows than needed] Crash cost/day ? ? ? ? ? ? ? ? Part C Max Crash Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. ? ? (A) List the critical activities (B) Completion time (normal time): (C) calculate crash cost per day (D), (E), and (F) Complete the tables (scroll down to see all of them). Write your answer in the text boxes provided. Part D: To get to 18 days, explain what you crashed (in order of crashing) and the total cost of the plan. Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Path Duration (Normal Time) Crash Crash Cost Direct Cost Indirect Cost Total Cost Path Part F: The Plan for the shortest possible time for this project (complete the table below - there maybe more columns/rows than needed) Duration (Normal Time) Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Crashi Crash Cost Direct Cost Indirect Cost Total Cost Iteration 1 Part E: To get to 16 days, explain what you crashed (in order of crashing) and the total cost of the plan. Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Part F: What is the shortest time to complete this project, how did you get to this timing (provide what was crashed and the order) and what is the total cost for this plan? tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing The the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $300/day. Complete the tables and write up your narrative in the text box provided. Activity A B C D Path E F G H Predecessor Normal Time B A, C A, C B D E, F Crash Crash Cost Direct Cost Indirect Cost Total Cost Duration (Normal Time) 5 4 7 2 3 8 5 6 Normal Cost $500 $400 $700 $200 $300 $800 $500 $600 Crash Time Crash Cost 3 2 6 1 - 5 4 3 $1,500 $2,000 $1,600 $500 $2,900 $1,000 $1,800 Part D: The Plan for 18 days (complete the table below - there maybe more columns/rows than needed] Crash cost/day ? ? ? ? ? ? ? ? Part C Max Crash Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. ? ? (A) List the critical activities (B) Completion time (normal time): (C) calculate crash cost per day (D), (E), and (F) Complete the tables (scroll down to see all of them). Write your answer in the text boxes provided. Part D: To get to 18 days, explain what you crashed (in order of crashing) and the total cost of the plan. Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Path Duration (Normal Time) Crash Crash Cost Direct Cost Indirect Cost Total Cost Path Part F: The Plan for the shortest possible time for this project (complete the table below - there maybe more columns/rows than needed) Duration (Normal Time) Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Crashi Crash Cost Direct Cost Indirect Cost Total Cost Iteration 1 Part E: To get to 16 days, explain what you crashed (in order of crashing) and the total cost of the plan. Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Part F: What is the shortest time to complete this project, how did you get to this timing (provide what was crashed and the order) and what is the total cost for this plan?
Expert Answer:
Related Book For
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill
Posted Date:
Students also viewed these accounting questions
-
Study the following reaction scheme: a. Identify the substances A to F by giving their names and formulae. b. Write a balanced chemical equation for the formation of gas B. c. (i) Describe a chemical...
-
Complete Table 5.1 to find each Box effect by calculating the Box average (Brand effect + grand mean). Crossed effects always sum to zero. Nested effects (Box) also sum to zero within each...
-
Scroll down to complete all parts of this task. Select from the option list provided the correct accounting treatment of gains and losses when the investment securities are reclassified. Each choice...
-
EarthTones, Inc., was a wholly owned subsidiary of Cutlinger Corporation. Several years ago, EarthTones acquired numerous oil leases and began exploration activities to determine their suitability...
-
Unique Boutique Inc. is considering two investment projects. The estimated net cash flows from each project are as follows: Each project requires an investment of $770,000. A rate of 15% has been...
-
Based on recent results, scores on the SAT test are normally distributed with a mean of 1511 and a standard deviation of 312. Scores on the ACT test are normally distributed with a mean of 21.1 and a...
-
Debentures of 30,000 are issued on 1 January 2003. Redemption is to take place, on equal terms, four years later. The company decides to put aside an equal amount to be invested at 5 per cent which...
-
Garden City Beach is a popular summer vacation destination for thousands of people. Each summer, the city hires temporary lifeguards to ensure the safety of the vacationing public. Garden Citys...
-
Big Rock Brewery currently rents a bottling machine for $55,000per? year, including all maintenance expenses. The company isconsidering purchasing a machine instead and is comparing twoalternate? 2...
-
Stewart Recording Studio, owned by Ron Stewart, showed the following bank reconciliation at March 31: A list of deposits made and cheques written during April, taken from the Cash Receipts Journal...
-
John Wayne is 50 years old and plans to retire in 20 years. His new employer provides 401K retirement plan and he plans to accumulate $1,000,000 in his retirement account by age of 70. Use Excel to...
-
Nanaimo Inn has 60 rooms and expects occupancy to be 70%. The owner wants to earn 10% return on total assets after tax. Total assets:$2,400,000 Income tax rate:25% Depreciation:straight line (20...
-
Variances should not be interpreted in isolation. The cause of a variance in one part of the value chain may be related to decisions made in another, for example, a favorable labor efficiency...
-
simplify lim h0 5(a + h) - 5a h
-
An auditor will take a SRS of 100 accounts from a firm's 600 accounts. Of the 600 accounts, 72 do not comply with company procedures. Let X be the count of the 100 sampled accounts that do not...
-
What accounts for their differing performance in China versus India ?
-
On January 1, 2021, Indigo Company purchased on credit machinery costing $186,000 and incurred $6,450 in installation costs. The machinery has an estimated useful life of 15 years and a residual...
-
Compare and contrast licensing and subcontracting.
-
Bev and Ken Hair have been married for 3 years. They live at 3567 River Street, Springfield, MO 63126. Ken is a full-time student at Southwest Missouri State University (SMSU) and Bev works as an...
-
David and Darlene Jasper have one child, Sam, who is 6 years old. The Jaspers reside at 4639 Honeysuckle Lane, Los Angeles, CA 90248. David's Social Security number is 577-11-3311, Darlene's is...
-
Quince Corporation has taxable income of $450,000 for its 2012 calendar tax year. Calculate the corporation's income tax liability for 2012 before tax credits. $_________
-
What is meant by "washing checks?"
-
Describe a lapping scheme and an audit step to discover lapping.
-
What is a cut-off bank reconciliation?
Study smarter with the SolutionInn App