Table.I Typical schedule (in months) Activity
Question:
Table.I Typical schedule (in months)
Activity Normal Time to Complete
Management go-ahead 0
Release of preliminary system specs. 6
Receipt of bids on specs. 2
Order hardware and systems software 2
Flow charts completed 2
Applications programs completed 3
Receipt of hardware and systems software 3
Testing and debugging done 2
Documentation, if required 2
Changeover completed 22
Develop a milestone schedule with all major milestones.
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray