The following input/output report was prepared for a work center with a beginning backlog of 23 hours:
Fantastic news! We've Found the answer you've been seeking!
Question:
The following input/output report was prepared for a work center with a beginning backlog of 23 hours:
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Planned input (hrs.) | 50 | 50 | 50 | 55 | 55 | 55 |
Actual input (hrs.) | 57 | 53 | 51 | 56 | 53 | 59 |
Cumulative deviation | | | | | | |
Planned output (hrs.) | 60 | 55 | 55 | 55 | 55 | 55 |
Actual output (hrs.) | 53 | 51 | 54 | 56 | 52 | 58 |
Cumulative deviation | | | | | | |
Actual backlog | | | | | | |
a. Complete the input/output report for the center.
b. Explain what the center was probably trying to accomplish, based on the planning numbers.