The following jobs are waiting to be processed in Rick Carlson's machine center. Carlson's machine center has a relatively long lead time and sets new
The following jobs are waiting to be processed in Rick Carlson's machine center. Carlson's machine center has a relatively long lead time and sets new schedules every 2 weeks, which does not alter previous schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is the start of day 241. At this time, there are no other jobs in progress or waiting to be worked. Jobs are due at the end of the day shown.
Job | Date of work received | production days needed | Job Due Date |
A | 225 | 25 | 270 |
B | 228 | 15 | 300 |
C | 230 | 35 | 325 |
D | 231 | 30 | 310 |
mi | 235 | 40 | 360 |
For the following 2 sequence rules, calculate the average flow time since today (consider that today, which is the start of day 241, is day 1 to determine the flow time), the average days late (no credit for being early), and the average number of days early (zero days in advance for a job that is late). The remaining workshop time is equal to the production days needed. The rules are as follows:
• Slack
• CR (Critical Ratio)
Step by Step Solution
3.40 Rating (150 Votes )
There are 3 Steps involved in it
Step: 1
To calculate the average flow time average days late and average number of days early for the given sequence rules Slack and CR we need to go through the jobs in the order determined by each rule and ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started