THE iterative software development method. Just read the case thoroughly and answer the below-mentioned 3 questions. Here
Question:
THE iterative software development method. Just read the case thoroughly and answer the below-mentioned 3 questions. Here are the three questions to be answered:
1. What are the two choices Lalonde has? If you think he has more than 2 choices, please list all the choices he has
2. Who should Lalonde and Mayor involve in the decision regarding the change request?
3. The Rational team is at their last 5 weeks of the entire development period of 18 months i.e. 72 weeks. The RAD team would need 6 weeks of time to go thru the iterative software development cycle where 4 weeks are allotted to planning, design, and implementation and the final 2 weeks are for the testing phase. How would you determine where to cut a week off the schedule to get it down to 5 weeks?