The monthly production schedule of the bicycle manufacturer is given below. Week Model one 2 3 4
Fantastic news! We've Found the answer you've been seeking!
Question:
The monthly production schedule of the bicycle manufacturer is given below.
Week
Model
one
2
3
4
B210
50
one hundred
200
150
G210
50
one hundred
200
150
B203
15
30
60
45
G203
15
30
60
45
B201
20
40
80
60
G201
20
40
80
60
The critical work center in the production of these bicycles is the welding center. The effectiveness of this center is 95 percent and its utilization is 90 percent. The time (in hours) required by each bike model in this center is given below:
B210
G210
B203
0.20
0.22
0.15
G203
B201
G201
0.17
0.07
0.09
Assume that the work center is available 40 hours a week. Calculate the weekly capacity and loading percentage of the work center and draw the weekly load profile.