The Rosie Pastry Company makes Rose-embellished birthday cake cookies in several large commercial bakeries across the United
Fantastic news! We've Found the answer you've been seeking!
Question:
As part of a continuous improvement program, W. Guan, a consultant from an external firm, wondered if the production process could be improved. To understand the process, she took a pencil and clipboard and drew a value stream map of the cookie process.
Guan knew that the monthly production requirement was 30,000 cases. The bakery operated 25 days per month with 3 8-hour shifts per day with an hour long lunch break. Since the line is dedicated to Rose-embellished birthday cake cookies, there is no changeover time or set up time.
Step 1: Mixing the dough involves combining the flour, shortening, sugar and cocoa and mixing. The processing time for one case is 50 seconds. There are two operators. Guan counted the inventory at the various storage locations and found ingredients for 1,200 cases of finished cookies before the mixer.
Step 2: Forming, baking and cooling are done by an automated production machine that holds 20 cases operating continuously at the same rate. The machine is able to form, bake & cool 20 cases every 15 minutes. That means 20 are finished every 15 minutes. Guan counted 300 cases of mixed dough before step 2.
Step 3: Guan counted 60 cases waiting to be iced & assembled. Icing and cookie assembly are done in a single operation, with three operators. The processing time is 12 minutes per case. Guan counted 600 cases before step 4.
Step 4: Finally, the processing time for packaging is 90 seconds per case. There is one operator and 60 cases waiting to be shipped.
The Sales department informs the Warehouse about sales forecasts. The Warehouse sends electronic forecasts and daily orders to Production Control. Production Control issues electronic purchase orders to the ingredient and packaging suppliers weekly but provides daily orders to each of the internal departments in the bakery.
Question 1
The available work time = ___________ min/day (enter integer).
Question 2
The customer demand is ______________ cases/day (enter integer).
Question 3
The takt time is _____________ seconds (enter integer).
Question 4
For the mixing step, full time employees (FTEs) = ________ (enter integer).
Question 5
For the mixing step, the cycle time is ______________ seconds (enter integer).
Question 6
For the second step, the cycle time is __________ seconds (enter integer).
Question 7
For the third step, the utilization is ____________ % (round to the nearest integer)?
Question 8
For the packaging step, the utilization is _______________ % (round to the nearest integer)?
Question 9
What is the total process time in seconds for all 4 steps (round to the nearest integer)?
Question 10
What is the total lead time in days (round to the nearest 1 decimal place)?