The scope, schedule, and cost baselines together are A. the performance measurement baseline B. the outputs of
Fantastic news! We've Found the answer you've been seeking!
Question:
The scope, schedule, and cost baselines together are
A. the performance measurement baseline
B. the outputs of the project management plan
C. included in the customers' contract or statement of work
D. finalized through the monitoring and controlling processes