. The tabulated summary below lists the cumulative values of Project 2079X (a 12 month project) with...
Fantastic news! We've Found the answer you've been seeking!
Question:
. The tabulated summary below lists the cumulative values of Project 2079X (a 12 month project) with values to the end of month 8.
MonthPCAC% Comp
1505010
21508020
326020030
437030045
549042055
659051065
770063575
880078080
9870
10930
11980
121000
a) What is the Budget at Completion (BAC) and Earned Value at the end of Month eight ? (10 marks)
[Answer here]
b) Looking at the project as a whole, describe the progress of the project thus far in terms of predicted schedule and cost implications. For each of these predicted implications (schedule and cost) provide a statement describing what might have caused