A contractor in Hong Kong has taken a construction project which allows for using the price fluctuation
Question:
A contractor in Hong Kong has taken a construction project which allows for using the price fluctuation factor (PFF) to calculate the contract price adjustment. The method for calculation is the Baxter method but with slight modification. Calculate the total price fluctuation factor based on the following assumptions.
There is no index figure for providing and maintaining plant in Hong Kong. The percentage for this aspect is apportioned among the other items. Thirty percent of it is added to labour cost and the remaining 70 per cent is added to the material costs.
Twenty per cent of the contract value is taken to be non-adjustable.
Fill the blanks in the following tables and calculate the amount of price adjustment.
Cost items | Agreed percentage of contract value | Add for plant | |||
Factor | Add to tender | Percentage | Proportion | ||
Labour | 25 | ||||
Steel bars | 15 | ||||
Concrete | 10 | ||||
Timber | 5 | ||||
Aggregate | 6 | ||||
Bricks | 2 | ||||
Diesel fuel | 12 | ||||
Bitumen | 5 | ||||
Provide and maintain plant | |||||
Total | |||||
All other costs not subject to adjustment | |||||
Total including non-adjustable items |
Cost items | Index | Proportional change | Index proportion | factor | |||
Base | Current | ||||||
Labour | 199 | 250 | |||||
Steel bars | 153 | 167 | |||||
Concrete | 201 | 211 | |||||
Timber | 200 | 150 | |||||
Aggregate | 157 | 190 | |||||
Bricks | 140 | 140 | |||||
Diesel fuel | 150 | 180 | |||||
Bitumen | 200 | 350 | |||||
Total Price fluctuation factor | |||||||
If the value of the work completed is 1.3 million HK dollar, what is the amount of price adjustment?