The total FOH planned for a company is $1,500,000 and the production amount for the same period
Fantastic news! We've Found the answer you've been seeking!
Question:
The total FOH planned for a company is $1,500,000 and the production amount for the same period is 2,000 units. 2.5 DL hours and 5 machine hours are required for each unit to produce. The company's cost accountant analysed the total FOH and found that 60% was related to machine hours and 40% to DL hours.
Find FOH application rates from DL and machine clock perspectives.