Using the information in the Job Sequencing Exercise, and the sequences assigned below, create two Gantt Charts
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the information in the Job Sequencing Exercise, and the sequences assigned below, create two Gantt Charts by loading the work centers with the available jobs. Based on your schedules, show the make spans, average total queue time across all jobs, and the total profit (loss) for your schedules. Briefly comment on your results.
Priority sequence and type of loading to use in developing your schedule:
USE ONLY BREAKOUT ROOM 8 INFORMATION PLEASE.
Transcribed Image Text:
JOB SEQUENCING PROBLEM The owner of a contract repair shop for small aircraft engines is faced with the problem of scheduling the various re- pair operations required on each engine. The type of repairs required varies from engine to engine. For various technical. reasons, the repairs on each engine must be made in a specified sequence of operations, which are performed at different "stations" in the shop, each station being manned by one mechanic. Thus, for example, one engine requiring 4 operations might follow the sequence "station 1, station 2, station 4, station 3," while another might follow the sequence "station 2, station 3, station 1, station." 11 A given engine does not necessarily pass through every station, and some engines may be routed through a given station more than once. As a result of equipment limitations there is only 1 station of each type, and the nature of the equipment is such that only 1 engine may be worked on at a station at any given time. Past experience has indicated that once an operation is begun at a particular station, work is most efficiently accomplished if the engine stays at that station until completion of the operation. The shop's contract with the aircraft owners specifies a fixed price for repairs of a given type on each engine type. Since most of the engines come from aircraft which are used in air taxi service, minimization of aircraft down time for repairs is important. Thus the contract calls for the establishment of a fixed due date. for each engine (usually 24-48 hours after engine acceptance at the shop). If the due date is not met, the repair shop is assessed a specific penalty for each hour of delay past the due date. Because of these facts, the shop owner customarily employs extra-shift personnel to provide for continuous work on each engine. On a typical morning, 3 engines have been accepted for repairs by the shop. The shop owner is attempting to lay out a work schedule for these 3 engines which will result in maximum total profit. Engine A is due at hour 33, Engine B is due at hour 26, and Engine C is due at hour 35. The contract price and delay penalty for each job (engine) are shown in Table 1 below. JOB SEQUENCING PROBLEM The owner of a contract repair shop for small aircraft engines is faced with the problem of scheduling the various re- pair operations required on each engine. The type of repairs required varies from engine to engine. For various technical. reasons, the repairs on each engine must be made in a specified sequence of operations, which are performed at different "stations" in the shop, each station being manned by one mechanic. Thus, for example, one engine requiring 4 operations might follow the sequence "station 1, station 2, station 4, station 3," while another might follow the sequence "station 2, station 3, station 1, station." 11 A given engine does not necessarily pass through every station, and some engines may be routed through a given station more than once. As a result of equipment limitations there is only 1 station of each type, and the nature of the equipment is such that only 1 engine may be worked on at a station at any given time. Past experience has indicated that once an operation is begun at a particular station, work is most efficiently accomplished if the engine stays at that station until completion of the operation. The shop's contract with the aircraft owners specifies a fixed price for repairs of a given type on each engine type. Since most of the engines come from aircraft which are used in air taxi service, minimization of aircraft down time for repairs is important. Thus the contract calls for the establishment of a fixed due date. for each engine (usually 24-48 hours after engine acceptance at the shop). If the due date is not met, the repair shop is assessed a specific penalty for each hour of delay past the due date. Because of these facts, the shop owner customarily employs extra-shift personnel to provide for continuous work on each engine. On a typical morning, 3 engines have been accepted for repairs by the shop. The shop owner is attempting to lay out a work schedule for these 3 engines which will result in maximum total profit. Engine A is due at hour 33, Engine B is due at hour 26, and Engine C is due at hour 35. The contract price and delay penalty for each job (engine) are shown in Table 1 below.
Expert Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 978-0133798074
4th edition
Authors: Jeffrey K. Pinto
Posted Date:
Students also viewed these accounting questions
-
Using the information in BE5-14, determine Martinezs free cash flow, assuming that it reported net cash provided by operating activities of $400,000.
-
Using the information in Exercise 16-5, assume that Landor Office Supplies records inventory on a perpetual basis and calculate the cost of the ending inventory under each of the following methods:...
-
Using the information in Exercise 1, if rent were increased by $25,000 and variable costs and unit selling price remained unchanged, what would be the new PV ratio and break-even point in units and...
-
You have three light bulbs; bulb A has a resistance of 240 , bulb B has a resistance of 192 , and bulb C has a resistance of 144 . Each of these bulbs is used for the same amount of time in a setup...
-
Choose one the four marks (Signs) of the church and thoroughly discuss it and its meaning today.
-
Of the bolts manufactured for a certain application, 90% meet the length specification and can be used immediately, 6% are too long and can be used after being cut, and 4% are too short and must be...
-
What is the purpose of the materials requisition?
-
Describe the nature and components of, and the issues currently facing, executive compensation in various U.S. industries.
-
Assume that company A wants to boost its stock price. The company currently has 13 million shares outstanding with a market price of $29 per share and no debt. A has had consistently stable earnings,...
-
Robinson Products Company has two service departments (S1 and S2) and two production departments (P1 and P2). The distribution of each service departments efforts (in percentages) to the other...
-
A user flow can be interpreted in many ways. It can be regarded as an overview that describes where users can navigate your product. It can also mean the actual quality and experience of the path...
-
ORIGINALLY CALLED INSTA-BURGER KING, the company was founded in Florida in 1953 by Keith Kramer and Matthew Burns. Their Insta-Broiler oven was so successful at cooking hamburgers that they required...
-
calculate kinetic energy at max height if compression distance is 0.08m, spring potential energy is 0.37440, max airborne Potential energy is 0.24768 and mass is 0.200kg and the max height is 0.126m
-
N 0 1 WN 2 3 4 5 T(z) 15 24 29 23 13 z=5m z=0m T(z) 5 2 2 Ay 3 Az T2 3 Ay perfect insulation material The above figure shows a cross-section of a copper alloy material embedded in a perfectly...
-
Prepare: Unadjusted trial balance, adjusting journal entries, t - accounts after adjusting journal entries, adjusted trial balance, financial statements, closing journal entires, t - accounts after...
-
A ramp used in lab 3: the height of the block is measured to be 10.25 cm, the distance between the support of the ramp is measuted to be 84.88 cm, whtat is the theoretical acceleration of the cart on...
-
(6 points) Here is a while loop written in Java. while (true) { } line readLine(); if (allBlanks (line)) break; consumeLine (line); If a programming language allows to use break to jump out of a...
-
Would you use the adjacency matrix structure or the adjacency list structure in each of the following cases? Justify your choice. a. The graph has 10,000 vertices and 20,000 edges, and it is...
-
Comment on the following statement: In deciding on whether or not to kill a project, it is critical to continually monitor the environment for signs it may no longer be viable.
-
Identify the five major methods for resolving conflict. Give an example of how each might be applied in a hypothetical project team conflict episode.
-
Identify the stage of group development. Why is it necessary for project teams to move through these stages in order to be productive?
-
Use chloroform to extract acetone from water. Equilibrium data are given in Table 13-6. Find number of equilibrium stages required for a countercurrent cascade if feed is \(1000.0 \mathrm{~kg} /...
-
We are extracting pyridine from \(500 \mathrm{~kg} / \mathrm{h}\) of a feed that is \(15.0 \mathrm{wt} \%\) pyridine and \(85.0 \mathrm{wt} \%\) water using \(225 \mathrm{~kg} / \mathrm{h}\) of pure...
-
Equilibrium for extraction of acetic acid from 3-heptanol into water at \(25^{\circ} \mathrm{C}\) is \(\mathrm{y}=1.208 \mathrm{x}\), where \(\mathrm{y}=\) weight fraction acetic acid in water and...
Study smarter with the SolutionInn App