Using the Network Diagram below, describe the relationships between each activity pertaining to lags. Notes: Ensure you
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the Network Diagram below, describe the relationships between each activity pertaining to lags.
Notes:
- Ensure you use proper terms such as "Start" and "Finish"
- Assume the lags are referring to "days"
- Activities can have multiple relationships
Activity | Lag Description |
F | Cannot start until Activity A finishes Cannot finish until 2 days after Activity E finishes |
E | |
D | |
C | |
B |