Value added activities problem Minutes Move raw materials from RM inventory to Machine A 6 Raw materials
Fantastic news! We've Found the answer you've been seeking!
Question:
Value added activities problem | Minutes |
Move raw materials from RM inventory to Machine A | 6 |
Raw materials wait to be put on machine A | 45 |
Time spent manufacturing product on Machine A | 180 |
Move from Machine A to Machine B | 5 |
Wait time before putting product on Machine B | 480 |
Time spent manufacturing product on Machine B | 120 |
Move from Machine B to Quality control department | 10 |
Time spent inspecting product | 240 |
Move product from QC to finished goods warehouse | 14 |
Total time in minutes | 1,100 |
Calculate the VA time as a % of total time.
Show solutions and calculations.