What activity / scope of work is the Work Plan developed for? (i.e. what is the crew
Fantastic news! We've Found the answer you've been seeking!
Question:
What activity / scope of work is the Work Plan developed for? (i.e. what is the crew being asked to do in the field?)
- What is to total contract value of the work included in this Work Plan?
- How many tolerances must the crew adhere to and verify in the field?
- In Step No. 7, to what depth must the backfill be added above the top of the pipe?
- When excavating the trenchline, what is the recommended spacing to set shores?
- When backfilling the trench, the slurry should be stopped how far below the existing utilities (like gas, phone, fiber, and water services)?
- When will the process take place to verify the tolerance that states "Variations from grade and alignment shall not exceed .1 FT"? (at what step will the tolerance check occur?)
- How many separate storm sewer crews are planned for the ARS Broadway Road Project as a whole?
- According to the 5-week look ahead, how many total weeks will this operation require?Briefly explain your answer.
- Explain why all Unit of Measure per Man-Hour (UOM / MH) numbers shown on page 1 are larger under the PRODUCTION GOALS (Financial Plan) section vs. the COST CODES & BUDGET SECTION?
- What are the top 3 things you found to be the best / most helpful about the Work Plan?
- What are the top 3 things you thought were missing? What could be improved?
Transcribed Image Text:
PKS Kiewit PLAN COMPLETED BY: OPERATION LOCATION: Segment 3 Prepared 2/4/15 SCOPE OF WORK: Excavate, Lay, and Backfill HDPE Storm Sewer Pipe COST CODES & BUDGET DESCRIPTION Unload and String HDPE ELB 18" HDPE - Mainline ELB 24" HDPE - Mainline ELB 30" HDPE - Mainline ELB 15"-18" HDPE - Laterals PRODUCTION GOALS (Financial Plan) Unload and String HDPE ELB 18" HDPE - Mainline ELB 24" HDPE - Mainline ELB 30" HDPE - Mainline ELB 15"-18" HDPE - Laterals EQUIPMENT 3/4 Ton Pickup 950 Loader 3/4 Ton Pickup 321 Excavator DESCRIPTION 950 Loader 950 Loader Walk Behind Roller (Rammex) SUPPLIES DESCRIPTION DESCRIPTION Shovels, Broom, & Digging Bars Ladders for each trench DESCRIPTION Pipe Bedding HDPE Pipe CLSM WBS 1158 1160 1161 1162 1159 ARS Broadway Road INSTALL STORM DRAIN WORKPLAN Paint, String-line, Plumb-bobs, Measuring tapes 10ft and 15ft. Lifting Slings and swivel hook Saw-zali and cutting blades Pipe lubricant Colored Cones PM'S QTY 4,010 2,248 758 103 901 QTY 4,010 2,248 758 103 901 UNIT LF LF LF LF LF QTY 4,329 TN 4,010 LF 615 CY UNIT LF LF LF LF LF 1 1 QTY Unload and String 1 1 1 1 UOM/MH 50.00 1.50 2.00 1.41 0.85 QTY 2 ea. As Req'd 2 ea. 2 ea. 1 ea. As Req'd 5 ea. color UOM/MH 53.75 1.61 2.15 1.52 0.91 YIELD 10% MANPOWER 3% 10% Load-out Spoils 1 ELB HDPE Mainline and Laterals Operator Foreman Operator Laborer UOM/HR 50.00 7.50 10.00 7.05 4.25 Operator Foreman Operator Laborer UOM/HR 53.75 8.06 10.75 7.58 4.57 DESCRIPTION Operator SUBS Total MH UNIT COST 80.20 1498.67 379.00 73.05 1060.00 SPECIAL TOOLS WAGE/HR TOTAL HOURLY $ 42.77 $ 40.91 $ 26.92 COST $ 42.77 $ 40.91 $ 26.92 TOTAL HOURLY COST TOTAL $ 0.74 $ 2,967.40 $ 23.79 $53,477.05 $ 17.84 $ 13,522.72 $ 25.27 $ 2,602.81 37,914.08 $ 42.08 $ Total MH 74.6 $ 0.68 $ 2,726.80 1396.3 $ 22.16 $49,815.68 352.56 $ 16.60 $ 12,582.80 67.76 $ 23.48 $ 2,418.44 990.1 $ 39.21 $ 35,328.21 $40.91 TOTAL HOURLY COST AGA SA SA SA Total: UNIT COST Total: QTY 1 1 1 1 2 2 1 DESCRIPTION Shoring, pump tools, release tools Rotating Laser, Grade-rods, Pipe Laser, Transit $ 110,484.06 TOTAL $ $ $ $ $ $ $ $ $ $ 102,871.93 COST/HR 42.77 40.91 26.92 110.60 42.77 81.82 53.84 178.43 40.91 40.91 QTY As Req'd 1 ea. H.W. Johnson - Catch Basin Form and Pour Olson Pre-Cast - Build Storm Drain Manholes SURVEY NEEDS (Attach Sketch) Staking every 50'. 15'-20' off sets to center line, Double stake M/H, Tees, Angle points (one each on opposite side of excavation or two in line 15' & 20' off set).Lath should have off set distance, cut to invert, stationing, & elevation of survey point. Also should denote M/H, Angle, Tee. Start, End, Etc. SAFETY DESCRIPTION Hazard Analysis Dig Permit Trench Insp. Form Shoring Insp. Form QUALITY ITEM SD GRADE/ALIGN COMPACTION BF MOISTURE DEFLECTION FIRST RULE OF SAFETY: Never Walk Past an Unsafe Act or Condition CRITICAL SAFETY CONCERNS/HAZARDS ISSUE REQUIRED(Y/N) Y Y Y Y 95 TO 100% + OR- 2% 1 DEGREE (4"/20") DONE BY: Foreman Foreman Foreman Foreman QUALITY ANALYSIS TOLERANCES .10 FOOT 4 - Excavate Trench line WHEN PRIOR TO START DAILY DAILY DAILY FIRST RULE OF QUALITY: Right the First Time POTENTIAL QUALITY ISSUES HOW VERIFIED? LASER/EYE LEVEL/TRANSIT DENISTY TESTS DENISTY TESTS LASER/TRANSIT/TAPE Trench Conditions Live Traffic Equipment 9 - Excavate for Storm Drain Manhole QUALITY ANALYSIS COMPLETED BY: Kevin Freeland HOLD POINTS IS unty cure over night before backill. 2 Check bedding grade before laying pipe 5- Place Pipe Bedding 6- Install Carrier Pipe 7 - Backfill Pipe Zone (Slurry) 8- Backfill Trench line W/ Native Material - Mainline Trenches ISSUE Damage to existing utilities Line and Grade Compaction 1 - Site Inspection - Verify Blue-Stake Dig Permit ***Review JHA w/ Crew. 2 - Verify Survey and Layout Excavation Centerline 3 - Excavation Guidelines - Shoring Plan/ Guidelines Pipe Joints Slurry Pipe Float WORK SEQUENCE / OPERATIONAL PLAN STEP BY STEP 10- Form and Pour Pipe Collars / SD Lateral Connections PREVENTION (Refer to Hazard Analysis) Proper trench sloping or shoring in place. Proper T/C and stay in-side work zone. Use Designated spotters/ eye contact. PREVENTION Blue-Stake / Dig Permit. Use of proper instruments / survey. Density testing of bedding and backfill. Keep clean / no debris inside pipe. Place slurry in small shallow lifts Review By: Initial & Date Foreman: Engineer: Field Supt: Project Mgr: PKS Kiewit PLAN COMPLETED BY: OPERATION LOCATION: Segment 3 Prepared 2/4/15 SCOPE OF WORK: Excavate, Lay, and Backfill HDPE Storm Sewer Pipe COST CODES & BUDGET DESCRIPTION Unload and String HDPE ELB 18" HDPE - Mainline ELB 24" HDPE - Mainline ELB 30" HDPE - Mainline ELB 15"-18" HDPE - Laterals PRODUCTION GOALS (Financial Plan) Unload and String HDPE ELB 18" HDPE - Mainline ELB 24" HDPE - Mainline ELB 30" HDPE - Mainline ELB 15"-18" HDPE - Laterals EQUIPMENT 3/4 Ton Pickup 950 Loader 3/4 Ton Pickup 321 Excavator DESCRIPTION 950 Loader 950 Loader Walk Behind Roller (Rammex) SUPPLIES DESCRIPTION DESCRIPTION Shovels, Broom, & Digging Bars Ladders for each trench DESCRIPTION Pipe Bedding HDPE Pipe CLSM WBS 1158 1160 1161 1162 1159 ARS Broadway Road INSTALL STORM DRAIN WORKPLAN Paint, String-line, Plumb-bobs, Measuring tapes 10ft and 15ft. Lifting Slings and swivel hook Saw-zali and cutting blades Pipe lubricant Colored Cones PM'S QTY 4,010 2,248 758 103 901 QTY 4,010 2,248 758 103 901 UNIT LF LF LF LF LF QTY 4,329 TN 4,010 LF 615 CY UNIT LF LF LF LF LF 1 1 QTY Unload and String 1 1 1 1 UOM/MH 50.00 1.50 2.00 1.41 0.85 QTY 2 ea. As Req'd 2 ea. 2 ea. 1 ea. As Req'd 5 ea. color UOM/MH 53.75 1.61 2.15 1.52 0.91 YIELD 10% MANPOWER 3% 10% Load-out Spoils 1 ELB HDPE Mainline and Laterals Operator Foreman Operator Laborer UOM/HR 50.00 7.50 10.00 7.05 4.25 Operator Foreman Operator Laborer UOM/HR 53.75 8.06 10.75 7.58 4.57 DESCRIPTION Operator SUBS Total MH UNIT COST 80.20 1498.67 379.00 73.05 1060.00 SPECIAL TOOLS WAGE/HR TOTAL HOURLY $ 42.77 $ 40.91 $ 26.92 COST $ 42.77 $ 40.91 $ 26.92 TOTAL HOURLY COST TOTAL $ 0.74 $ 2,967.40 $ 23.79 $53,477.05 $ 17.84 $ 13,522.72 $ 25.27 $ 2,602.81 37,914.08 $ 42.08 $ Total MH 74.6 $ 0.68 $ 2,726.80 1396.3 $ 22.16 $49,815.68 352.56 $ 16.60 $ 12,582.80 67.76 $ 23.48 $ 2,418.44 990.1 $ 39.21 $ 35,328.21 $40.91 TOTAL HOURLY COST AGA SA SA SA Total: UNIT COST Total: QTY 1 1 1 1 2 2 1 DESCRIPTION Shoring, pump tools, release tools Rotating Laser, Grade-rods, Pipe Laser, Transit $ 110,484.06 TOTAL $ $ $ $ $ $ $ $ $ $ 102,871.93 COST/HR 42.77 40.91 26.92 110.60 42.77 81.82 53.84 178.43 40.91 40.91 QTY As Req'd 1 ea. H.W. Johnson - Catch Basin Form and Pour Olson Pre-Cast - Build Storm Drain Manholes SURVEY NEEDS (Attach Sketch) Staking every 50'. 15'-20' off sets to center line, Double stake M/H, Tees, Angle points (one each on opposite side of excavation or two in line 15' & 20' off set).Lath should have off set distance, cut to invert, stationing, & elevation of survey point. Also should denote M/H, Angle, Tee. Start, End, Etc. SAFETY DESCRIPTION Hazard Analysis Dig Permit Trench Insp. Form Shoring Insp. Form QUALITY ITEM SD GRADE/ALIGN COMPACTION BF MOISTURE DEFLECTION FIRST RULE OF SAFETY: Never Walk Past an Unsafe Act or Condition CRITICAL SAFETY CONCERNS/HAZARDS ISSUE REQUIRED(Y/N) Y Y Y Y 95 TO 100% + OR- 2% 1 DEGREE (4"/20") DONE BY: Foreman Foreman Foreman Foreman QUALITY ANALYSIS TOLERANCES .10 FOOT 4 - Excavate Trench line WHEN PRIOR TO START DAILY DAILY DAILY FIRST RULE OF QUALITY: Right the First Time POTENTIAL QUALITY ISSUES HOW VERIFIED? LASER/EYE LEVEL/TRANSIT DENISTY TESTS DENISTY TESTS LASER/TRANSIT/TAPE Trench Conditions Live Traffic Equipment 9 - Excavate for Storm Drain Manhole QUALITY ANALYSIS COMPLETED BY: Kevin Freeland HOLD POINTS IS unty cure over night before backill. 2 Check bedding grade before laying pipe 5- Place Pipe Bedding 6- Install Carrier Pipe 7 - Backfill Pipe Zone (Slurry) 8- Backfill Trench line W/ Native Material - Mainline Trenches ISSUE Damage to existing utilities Line and Grade Compaction 1 - Site Inspection - Verify Blue-Stake Dig Permit ***Review JHA w/ Crew. 2 - Verify Survey and Layout Excavation Centerline 3 - Excavation Guidelines - Shoring Plan/ Guidelines Pipe Joints Slurry Pipe Float WORK SEQUENCE / OPERATIONAL PLAN STEP BY STEP 10- Form and Pour Pipe Collars / SD Lateral Connections PREVENTION (Refer to Hazard Analysis) Proper trench sloping or shoring in place. Proper T/C and stay in-side work zone. Use Designated spotters/ eye contact. PREVENTION Blue-Stake / Dig Permit. Use of proper instruments / survey. Density testing of bedding and backfill. Keep clean / no debris inside pipe. Place slurry in small shallow lifts Review By: Initial & Date Foreman: Engineer: Field Supt: Project Mgr:
Expert Answer:
Answer rating: 100% (QA)
Based on the provided work plan for the ARS Broadway Road project here are the key points and answer... View the full answer
Related Book For
Intermediate Accounting IFRS
ISBN: 978-1119372936
3rd edition
Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield
Posted Date:
Students also viewed these general management questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
KYC's stock price can go up by 15 percent every year, or down by 10 percent. Both outcomes are equally likely. The risk free rate is 5 percent, and the current stock price of KYC is 100. (a) Price a...
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
15. The temperature C, in degrees, that is equivalent to a temperature of F degrees Fahrenheit is given by C- graph of this equation shows the temperature in Celsius for the corresponding...
-
A force acts at the origin of a coordinate system in a direction defined by the angles x= 70.9 and y = 144.9. Knowing that the z component of the force is -52.0 lb, determine (a) The angle z, (b) The...
-
HUDSON COMPANY Contribution Margin Income Statement For Year Ended December 31 Sales (9,600 units at $225 each) Variable costs (9,600 units at $180 each) Contribution margin Fixed costs Income...
-
The following data available for four stroke petrol engine : bore \(=20 \mathrm{~cm}\) stroke to bore ratio \(=\) 1.5 , speed \(=350 \mathrm{rpm}, \mathrm{p}_{\mathrm{m}}=2.75 \mathrm{bar}\), net...
-
Jobs A, B, C, and D must be processed through the same machine center. Sequence the following jobs by (a) SPT (b) SLACK. Calculate mean flow time, mean tardiness, and maximum tardiness. Which...
-
Holland has been down to the Law Clinic and has returned with several new cases/clients; Wanda and the doorman from the 7-Seas Bar/Grill,Wanda, who has been charged with malicious destruction of a...
-
A firm has an expected free cash flow of $1,238,473 by the end of 2018 that is expected to be constant at this level beyond this year forever. If its cost of capital is 9%. What is the value of this...
-
Study each of the cases below. Indicate whether the contract is executed, executory, or neither, and whether it is valid, voidable, or void, by placing an X in the space provided. Knoll and Kalichuk...
-
You work for a telecommunications company and your current project is to determine the five African countries that, in your estimation, should have an advantage in telecommunications infrastructure....
-
Purposely not disclosing material facts to a contracting party. a. contract of adhesion b. duress c. fraud d. intentional c oncealment e. misrepresentation f. mistake g. mutual a greement h. puffi ng...
-
For several years now the European Union, the largest regional trading bloc in the world, has been trying to liberalize its energy market, replacing the markets of its 27 member states with a single...
-
A belief not in accord with the facts that may be concerned with the nature of the subject matter or the quality of the subject matter. a. contract of adhesion b. duress c. fraud d. intentional c...
-
There is a medical test for a virus. The test is 95% accurate (i.e., it indicates positive 95% of the time when the individual has actually the virus, as it also indicates negative 95% of the time...
-
Use critical values to test the null hypothesis H0: 1 2 = 20 versus the alternative hypothesis H0: 1 2 20 by setting a equal to .10, .05, .01, and .001. How much evidence is there that the...
-
In 2019, Sato Ltd. received a grant for 2 million to defray the cost of purchasing research equipment for its manufacturing facility. The total cost of the equipment is 10 million. Prepare the...
-
The financial records of Dunbar Inc. were destroyed by fire at the end of 2019. Fortunately, the controller had kept the following statistical data related to the income statement. 1. The beginning...
-
Bedard Ltd. reported net income of 300,000 in 2019 and had 200,000 ordinary shares outstanding throughout the year. Also outstanding all year were 45,000 options to purchase ordinary shares at 10 per...
-
The responses most likely to be associated with use of a force-coercion change strategy are best described as __________. (a) internalized commitment (b) temporary compliance (c) passive cooptation...
-
The assessment center approach to employee selection relies heavily on ____________ to evaluate a candidates job skills. (a) intelligence tests (b) simulations and experiential exercises (c) 360...
-
Which of the following questions can an interviewer legally ask a job candidate during a telephone interview? (a) Are you pregnant or planning to soon start a family? (b) What skills do you have that...
Study smarter with the SolutionInn App