What do we calculate when we subtract the Earliest Start time ( ES ) from the Latest
Fantastic news! We've Found the answer you've been seeking!
Question:
What do we calculate when we subtract the Earliest Start time ES from the Latest Start time LS in a project network?
Question options:
Earliest finish time
Project delay
Critical time
Activity Slack