What is the probability of completing this project within 25 weeks? Assume that the expected completion time
Fantastic news! We've Found the answer you've been seeking!
Question:
What is the probability of completing this project within 25 weeks? Assume that the expected completion time is 26 weeks.
Optimistic, Most probable, and pessimistic Activity time Estimates (in Weeks) | |||
Activity | Optimistic (a) | Most Probable (m) | Pessimistic (b) |
A | 4.00 | 7.00 | 12.00 |
B | 1.00 | 2.00 | 5.00 |
C | 2.00 | 4.00 | 7.00 |
D | 3.00 | 5.00 | 11.00 |
E | 2.00 | 4.00 | 6.00 |
F | 1.50 | 3.00 | 5.00 |
G | 1.50 | 4.00 | 4.50 |
H | 2.50 | 4.00 | 7.50 |
I | 1.50 | 3.00 | 3.50 |
J | 1.00 | 2.00 | 3.00 |
Activity | Earliest Start (ES) | Latest Start (LS) | Earliest Finish (EF) | Latest Finish (LF) |
A | 0 | 0 | 6 | 6 |
B | 0 | 7 | 2 | 9 |
C | 6 | 10 | 9 | 13 |
D | 6 | 7 | 11 | 12 |
E | 6 | 6 | 9 | 9 |
F | 9 | 13 | 11 | 15 |
G | 11 | 12 | 14 | 15 |
H | 9 | 9 | 13 | 13 |
I | 13 | 13 | 15 | 15 |
J | 15 | 15 | 17 | 17 |