Which scheduling technique in project management uses the longest chain of consecutively dependent tasks? Question 1 1
Fantastic news! We've Found the answer you've been seeking!
Question:
Which scheduling technique in project management uses the longest chain of consecutively dependent tasks?
Question options:
PERT
Goldratt's Critical Chain
CPM
Gantt charts