X purchased land and then erected a building. The following costs incurred were: Purchase price of land
Fantastic news! We've Found the answer you've been seeking!
Question:
X purchased land and then erected a building. The following costs incurred were:
Purchase price of land | 1,000,000 |
Resource consent fees | 70,000 |
Architects and Engineers fees | 100,000 |
Construction of Building | 1,500,000 |
Interest costs in relation to the Building (over the period) | 180,000 |
The Building became available for use 3 months into the financial year ended 31 March 2017.
- Calculate Depreciation using the Straight Line Method at 2.5% for this year; there is a nil residual value.
- Calculate depreciation for the year ended 31 March 2018