XYZ Company just hired you as a production manager for their North American manufacturing facility. His first job is to use the MRP methodology to schedule production for the next nine weeks. XYZ Company has provided you with the following information to work with:
Bill of Materials and Current Inventory Records:
Article | Padre | Delivery time (in weeks) | Lot Size | Inventory currently available |
A | none | 1 | batch by batch | 0 |
B | A | 2 | batch by batch | 0 |
C | A | 3 | 100 | 52 |
Master production schedule:
Article | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | Week 9 |
A | 0 | 0 | 0 | 15 | 0 | 60 | 0 | 36 | 75 |
You can take on one-to-one parent/child requirements when assembling this particular product structure. Which of the following are true statements about Week 3 of your plan?
I. An order of 15 of Item B will be received.
II. An order of 60 of Item B (planned order release) will be placed.
3rd There will be 66 of item C in inventory at the end of week 3.