You are in charge of a project at the local community center. The center needs to...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity START A B C D E F G H FINISH Normal Time (days) 0 8 7 3 8 5 8 4 6 0 Normal Cost (S) 0 50 40 70 20 30 80 50 60 D Crash Time (days) 0 7 3 1 6 5 A 1 4 0 Crash Cost ($) Immediate Predecessor(s) 0 180 360 310 100 30 520 320 100 a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is 22 days. (Enter your response as an integer.) b. Suppose the variable overhead costs are $30 per day for your project. Also, suppose that the center must pay $80 per day for a temporary room on day 17 or beyond. Find the minimum-cost project schedule. Fill in the table below to show the proper schedule (time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers.) Activity Time (days) Activity Time (days) A 8 E B F D G H L START START B A, C A.C B D E. F G, H E You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity START A B C D E F G H FINISH Normal Time (days) 0 8 7 3 8 5 8 4 6 0 Normal Cost (S) 0 50 40 70 20 30 80 50 60 D Crash Time (days) 0 7 3 1 6 5 A 1 4 0 Crash Cost ($) Immediate Predecessor(s) 0 180 360 310 100 30 520 320 100 a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is 22 days. (Enter your response as an integer.) b. Suppose the variable overhead costs are $30 per day for your project. Also, suppose that the center must pay $80 per day for a temporary room on day 17 or beyond. Find the minimum-cost project schedule. Fill in the table below to show the proper schedule (time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers.) Activity Time (days) Activity Time (days) A 8 E B F D G H L START START B A, C A.C B D E. F G, H E
Expert Answer:
Answer rating: 100% (QA)
Activity A B Time days 8 6 Normal Cost 50 60 Crash Cost 100 80 Crash ... View the full answer
Related Book For
Operations management processes and supply chain
ISBN: 978-0136065760
9th edition
Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra
Posted Date:
Students also viewed these accounting questions
-
you will be given three errors that may or may not affect the trial balance. You are to determine the following: 1. As a result of each error, will the trial balance still balance? Consider each...
-
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent...
-
What is path dependence? Explain the concept using your own words and provide an example of path dependence (other than what we have already mentioned in class). List the 4 categories of innovation,...
-
Refer to your solution for Exercise 3-14. Cash ..................................................................$53,200 Accounts payable .................................................9,500 Jin...
-
Evaluating Hedging With Futures Contracts A large farming company likes to firm up prices for its agricultural products. It anticipates harvesting and selling 1,000,000 bushels of a particular...
-
You need to understand the approach described in question 3 in More Genetic TIPS before answering this question. A muscle-specific gene was cloned and then subjected to promoter bashing. As shown...
-
Flush Mate Co. wholesales bathroom fixtures. During the current fiscal year, Flush Mate Co. received the following notes: Instructions 1. Determine for each note (a) The due date (b) The amount of...
-
3 Eight students were asked to estimate the mass of a bag of sweets in grams. First they were asked to estimate the mass without touching the bag and then they were told to pick the bag up and...
-
Which of the following statements is true of a virtual privatecloud (VPC)? A VPC does not make use of a VPN (virtual private network). A VPC can be accessed only from within anorganization. A VPC can...
-
What is the importance of exchange rates in judicial awards? Explain the difference between the breach date and the judgment date. Should plaintiffs be compensated for exchange rate volatility? Why?...
-
Was the Abu Dhabi formula inhibitive and akin to indirect expropriation? Could there have been a public purpose for Decree Law No. 124? Why? What are some of the economic and investment implications...
-
Can outsiders misappropriate financial information? How? Critically discuss the difference between outsider misappropriation of financial information and insider trading.
-
Customers enter the waiting line at a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, and service times follow an exponential distribution. If the...
-
Referring to similarly situated cases, did the Kuwaiti Government engage in unfair and discriminatory treatment to foster an illegal expropriation of the assets of Aminoil?
-
The company has now been in business 3 years. Nick has been working on growing within the industry and paying down debt. Nick is hoping that some additional analysis can be completed on his business...
-
Economic feasibility is an important guideline in designing cost accounting systems. Do you agree? Explain.
-
Canon, a Japanese manufacturer of photographic equipment, decided against offshoring and kept its manufacturing and new product development processes in Japan, which has relatively high labor costs,...
-
Compare and contrast the following two situations: a. A companys lean system stresses teamwork. Employees feel more involved and, therefore, productivity and quality increase at the company. The...
-
Build-Rite Construction has received favorable publicity from guest appearances on a public TV home improvement program. Public TV programming decisions seem to be unpredictable, so Build Rite cannot...
-
Parents with a child in subsidized childcare in the province of Qubec, Canada, pay a basic amount and, depending on family income, may pay an additional amount. As of January 1, 2017, families with a...
-
A firm in the state of Karnataka in India can source one of its factors of production either within the state, \(F_{K}\), or from the neighboring state of Maharashtra, \(F_{M}\). Assume the quality...
-
A firm has the cost curve \(C(q)=25+q^{2}\). Show how the firm's average cost varies with output. Is there a minimum average cost and, if so, at what level of output is average cost minimized?
Study smarter with the SolutionInn App