You are running a project in one of your companys manufacturing plants. After 25 weeks of the
Question:
You are running a project in one of your company’s manufacturing plants. After 25 weeks of the project, your earned value dataset is shown below. Use the information provided to answer the questions below. The project is planned to end in week 30, with a planned budget of $135 000. You are currently at the end of week 25. Describe what the results of each calculation mean to you as a project manager. The values are in dollars.
Planned Value (PV) = $100 000
Earned Value (EV) = $79 000
Actual Value (AC) = $110 000
i. What is the estimated Schedule Variance (SV) and its interpretation?
ii. What is the estimated Cost Variance (CV) and its interpretation?
iii. What is the estimated SPI and its interpretation?
iv. What is the estimated CPI and its interpretation?
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill