You are the contracting officer for a CPFF service contract for routine and emergency maintenance of testing
Question:
You are the contracting officer for a CPFF service contract for routine and emergency maintenance of testing equipment in the amount of $1,200,000. The contractor is not required to provide any supplies under this contract. The requiring activity has just notified you that it would like to add the maintenance repair of the noncommercial electrical boxes that are tested with the equipment to this contract.
Answer these questions:
1. What changes clauses are applicable to this contract?
2. Can this proposed change be made pursuant to the applicable changes clause?
3. How might you execute the requiring activity's request for change? (citation not required)
Financial Reporting Financial Statement Analysis and Valuation a strategic perspective