You are the manager if an IT project to develop and install a customer relationship management...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
You are the manager if an IT project to develop and install a customer relationship management (CRM) module within your company's enterprise IT system. So far, you have planned only the first phase of the project, which doesn't include the soft launch (to test the system live), user input, corrections, or final launch. A network diagram showing the first phase of project schedule appears below. Costs are spread evenly over the activity times. Use the tabs in this spreadsheet to complete this assignment. Task 1- Create a Baseline Budget for this project (use Tab: Task 1 - Baseline Budget) (25 Points) Task 2 - The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, if the project progress continues in this way. (50 Points) Assess User Requirements (4 Weeks, $24,000) Assess Current System (2 Weeks, $16,000) Send RFP for Software Vendors (1 Week, $10,000) The CRM PROJECT Specify System Requirements (2 Weeks, $32,000) Send RFP for Hardware Vendors (2 Weeks, $10,000) Select Software Vendor and Prep. Contract (1 Week, $4,000) Program and Test the Module (6 Weeks, $150,000) Select Hardware Vendor and Prep. Contract (1 Week, $3000) Train Users (3 Weeks, $75,000) Task 1: Complete the baseline budget for this project. Assume that the budget for an activity is used uniformly during its duration. Task 1- Create a Baseline Budget for this project (use Tab: Task 1 - Baseline Budget) (25 Points) Project: CRM Budget 3 Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Assess User Requirements (4 Weeks, $24,000) Assess Current System (2 Weeks, $16,000) $24,000 $16,000 $32,000 $10,000 $10,000 $4,000 $3,000 $150,000 $75,000 Send RFP for Software Vendors (1 Week, $10,000) Specify System Requirements (2 Weeks, $32,000) Send RFP for Hardware Vendors (2 Weeks, $10,000) Select Software Vendor and Prep. Contract (1 Week, $4,000) Program and Test the Module (6 Weeks, $150,000) Select Hardware Vendor and Prep. Contract (1 Week, $3000) Train Users (3 Weeks, $75,000) 6 8 9 10 11 12 13 What is the budget at completion for this project What is the expected completion time for this pr 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Task 1: Complete the baseline budget for this project. Assume that the budget for an activity is used uniformly during its duration. Task 1- Create a Baseline Budget for this project (use Tab: Task 1 - Baseline Budget) (25 Points) Project: CRM Budget 3 Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Assess User Requirements (4 Weeks, $24,000) Assess Current System (2 Weeks, $16,000) $24,000 $16,000 $32,000 $10,000 $10,000 $4,000 $3,000 $150,000 $75,000 Send RFP for Software Vendors (1 Week, $10,000) Specify System Requirements (2 Weeks, $32,000) Send RFP for Hardware Vendors (2 Weeks, $10,000) Select Software Vendor and Prep. Contract (1 Week, $4,000) Program and Test the Module (6 Weeks, $150,000) Select Hardware Vendor and Prep. Contract (1 Week, $3000) Train Users (3 Weeks, $75,000) 6 8 9 10 11 12 13 What is the budget at completion for this project What is the expected completion time for this pr 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Project: CRM Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Activity Assess User Requirements Assess Current System Cumulative Week 8 Activity Assess User Requirements Budget Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Cumulative 2 $20,000 $5,000 $5,000 $30,000 $10,000 $10,000 $30,000 $15,000 $15,000 $7,000 $8,000 $200,000 $100,000 % Complete AC 100% $20,000 100% $32,000 % Complete AC 100% $20,000 100% $32,000 100% $18,000 75% 100% $13,000 $15,000 EV 3 $5,000 $5,000 $10,000 EV PV PV SV SV CV $15,000 CV 6 $15,000 7 $10,000 $2,500 $10,000 $5,000 CPI SPI 8 sk 2 - The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, ? if the project progress continues in this way. (50 Points) Week 4 CPI SPI 9 $2,500 $8,000 BAC Planned Duration Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI 10 Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI $7,000 11 12 13 $25,000 $25,000 $25,000 14 15 $25,000 $25,000 What is your overall assessment at this period (Week 8), does it appear that the project is likely to finish on-time and on-budget? Why or why not? Explain your assessment (your response should not exceed the space provided here). 16 $25,000 17 $25,000 18 $25,000 19 $25,000 20 21 22 $25,000 $25,000 $25,000 Project: CRM Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Activity Assess User Requirements Assess Current System Cumulative Week 8 Activity Assess User Requirements Assess Current System Specify System Requirements Budget Send RFP for Software Vendors Send RFP for Hardware Vendors Cumulative 2 $20,000 $5,000 $5,000 $5,000 $5,000 $30,000 $10,000 $10,000 $10,000 $30,000 $15,000 $15,000 $7,000 $8,000 $200,000 $100,000 % Complete AC 100% $20,000 100% $32,000 % Complete AC 100% $20,000 100% $32,000 100% $18,000 75% 100% $13,000 $15,000 EV EV PV PV SV SV CV 5 $15,000 CV $15,000 Task 2 - The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, if the project progress continues in this way. (50 Points) Week 4 $10,000 $2,500 $10,000 $5,000 8 CPI SPI 9 CPI SPI $2,500 $8,000 BAC Planned Duration Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI 10 Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI $7,000 11 12 13 ? ? 14 15 16 What is your overall assessment at this period (Week 8), does it appear that the project is likely to finish on-time and on-budget? Why or why not? Explain your assessment (your response should not exceed the space provided here). 17 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 18 19 20 21 22 $25,000 $25,000 $25,000 $25,000 You are the manager if an IT project to develop and install a customer relationship management (CRM) module within your company's enterprise IT system. So far, you have planned only the first phase of the project, which doesn't include the soft launch (to test the system live), user input, corrections, or final launch. A network diagram showing the first phase of project schedule appears below. Costs are spread evenly over the activity times. Use the tabs in this spreadsheet to complete this assignment. Task 1- Create a Baseline Budget for this project (use Tab: Task 1 - Baseline Budget) (25 Points) Task 2 - The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, if the project progress continues in this way. (50 Points) Assess User Requirements (4 Weeks, $24,000) Assess Current System (2 Weeks, $16,000) Send RFP for Software Vendors (1 Week, $10,000) The CRM PROJECT Specify System Requirements (2 Weeks, $32,000) Send RFP for Hardware Vendors (2 Weeks, $10,000) Select Software Vendor and Prep. Contract (1 Week, $4,000) Program and Test the Module (6 Weeks, $150,000) Select Hardware Vendor and Prep. Contract (1 Week, $3000) Train Users (3 Weeks, $75,000) Task 1: Complete the baseline budget for this project. Assume that the budget for an activity is used uniformly during its duration. Task 1- Create a Baseline Budget for this project (use Tab: Task 1 - Baseline Budget) (25 Points) Project: CRM Budget 3 Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Assess User Requirements (4 Weeks, $24,000) Assess Current System (2 Weeks, $16,000) $24,000 $16,000 $32,000 $10,000 $10,000 $4,000 $3,000 $150,000 $75,000 Send RFP for Software Vendors (1 Week, $10,000) Specify System Requirements (2 Weeks, $32,000) Send RFP for Hardware Vendors (2 Weeks, $10,000) Select Software Vendor and Prep. Contract (1 Week, $4,000) Program and Test the Module (6 Weeks, $150,000) Select Hardware Vendor and Prep. Contract (1 Week, $3000) Train Users (3 Weeks, $75,000) 6 8 9 10 11 12 13 What is the budget at completion for this project What is the expected completion time for this pr 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Task 1: Complete the baseline budget for this project. Assume that the budget for an activity is used uniformly during its duration. Task 1- Create a Baseline Budget for this project (use Tab: Task 1 - Baseline Budget) (25 Points) Project: CRM Budget 3 Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Assess User Requirements (4 Weeks, $24,000) Assess Current System (2 Weeks, $16,000) $24,000 $16,000 $32,000 $10,000 $10,000 $4,000 $3,000 $150,000 $75,000 Send RFP for Software Vendors (1 Week, $10,000) Specify System Requirements (2 Weeks, $32,000) Send RFP for Hardware Vendors (2 Weeks, $10,000) Select Software Vendor and Prep. Contract (1 Week, $4,000) Program and Test the Module (6 Weeks, $150,000) Select Hardware Vendor and Prep. Contract (1 Week, $3000) Train Users (3 Weeks, $75,000) 6 8 9 10 11 12 13 What is the budget at completion for this project What is the expected completion time for this pr 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Project: CRM Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Activity Assess User Requirements Assess Current System Cumulative Week 8 Activity Assess User Requirements Budget Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Cumulative 2 $20,000 $5,000 $5,000 $30,000 $10,000 $10,000 $30,000 $15,000 $15,000 $7,000 $8,000 $200,000 $100,000 % Complete AC 100% $20,000 100% $32,000 % Complete AC 100% $20,000 100% $32,000 100% $18,000 75% 100% $13,000 $15,000 EV 3 $5,000 $5,000 $10,000 EV PV PV SV SV CV $15,000 CV 6 $15,000 7 $10,000 $2,500 $10,000 $5,000 CPI SPI 8 sk 2 - The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, ? if the project progress continues in this way. (50 Points) Week 4 CPI SPI 9 $2,500 $8,000 BAC Planned Duration Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI 10 Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI $7,000 11 12 13 $25,000 $25,000 $25,000 14 15 $25,000 $25,000 What is your overall assessment at this period (Week 8), does it appear that the project is likely to finish on-time and on-budget? Why or why not? Explain your assessment (your response should not exceed the space provided here). 16 $25,000 17 $25,000 18 $25,000 19 $25,000 20 21 22 $25,000 $25,000 $25,000 Project: CRM Assess User Requirements Assess Current System Specify System Requirements Send RFP for Software Vendors Send RFP for Hardware Vendors Select Software Vendor Select Hardware Vendor Program and Test the Module Train Users Cumulative Activity Assess User Requirements Assess Current System Cumulative Week 8 Activity Assess User Requirements Assess Current System Specify System Requirements Budget Send RFP for Software Vendors Send RFP for Hardware Vendors Cumulative 2 $20,000 $5,000 $5,000 $5,000 $5,000 $30,000 $10,000 $10,000 $10,000 $30,000 $15,000 $15,000 $7,000 $8,000 $200,000 $100,000 % Complete AC 100% $20,000 100% $32,000 % Complete AC 100% $20,000 100% $32,000 100% $18,000 75% 100% $13,000 $15,000 EV EV PV PV SV SV CV 5 $15,000 CV $15,000 Task 2 - The project plan gets revised and you now have a new baseline budget given to you (Tab: Revised Budget) go to this worksheet and complete all the entries the EVM tables given for each update. Then, at the end period 8, give an assessment on project's progress in terms of its budget and schedule, if the project progress continues in this way. (50 Points) Week 4 $10,000 $2,500 $10,000 $5,000 8 CPI SPI 9 CPI SPI $2,500 $8,000 BAC Planned Duration Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI 10 Forecast for cost (EAC)? Forecast for completion time (ETC Time)? TCPI $7,000 11 12 13 ? ? 14 15 16 What is your overall assessment at this period (Week 8), does it appear that the project is likely to finish on-time and on-budget? Why or why not? Explain your assessment (your response should not exceed the space provided here). 17 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 $25,000 18 19 20 21 22 $25,000 $25,000 $25,000 $25,000
Expert Answer:
Related Book For
Modern Systems Analysis And Design
ISBN: 9780134204925
8th Edition
Authors: Joseph Valacich, Joey George
Posted Date:
Students also viewed these accounting questions
-
1. The BOM inventory at retail for budget footwear for Gallop's Department Store was $30,000 on August 1st, with an inventory planned at $40,000 on August 31. Planned sales were $14,000, with...
-
Planning is one of the most important management functions in any business. A front office managers first step in planning should involve determine the departments goals. Planning also includes...
-
THIRD AVENUE SOFTWARE HEALTH-CARE APP PROJECT This case is new for the ninth edition of Information Technology Project Management . The case provides an opportunity to apply agile and Scrum...
-
The system shown consists of 3 cables. For example; cable C12 joins points 1 and 2. The coordinates of point 1 are (6.4, 0, 0) m, those of point 2 are (0, 9.5, -6.1) m, and those of point 3 are (0,...
-
What is the function of osteoclasts and why are they needed?
-
Find each root. V0.36
-
Use the abbreviated comparative financial statements for West Coast Construction, Inc. in the Working Papers. Instructions: 1. Review the comparative income statement and identify the amounts of net...
-
Whaley Distributors is a wholesale distributor of electronic components. Financial statements for the years ended December 31, 2009 and 2010, reported the following amounts and subtotals ($ in...
-
When reviewing a rating unit's operating performance, which one of the following ratios indicates whether an insurer has made an underwriting loss or gain? Available answer options Select only one...
-
Amadeus Corporation is considering the issue of a new product to be added to its product mix. They hired you, a recent business graduate from MacEwan, for conducting the analysis. The production line...
-
Parker Corporation uses a job costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Last year, manufacturing overhead costs and...
-
Suppose the articles of incorporation authorize 20 million shares of common stock. To date, 12 million have been issued. Currently there are 500,000 shares in treasury. How many shares are...
-
Prepare Sally Jensen's 2022 tax return in Profile. Submit the entire return in one PDF file. Information relating to Sally's tax return: 1. Sally is married to Peter Jensen. 2. Peter has net income...
-
Westham Industries is studying the profitability of a change in operation and has gathered the following information: Current Operation Anticipated Operation Fixed costs $ 38,600 $ 50,600 Selling...
-
A 4-ft-high, 3-ft-diameter cylindrical water tank whose top is open to the atmosphere is initially filled with water. Now the discharge plug near the bottom of the tank is pulled out, and a water jet...
-
Farrow Company reports the following annual results. Contribution Margin Income Statement Per Unit Annual Total Sales (440,000 units) $ 15.00 $ 6,600,000 Variable costs Direct materials 2.00 880,000...
-
Probability of the state of economy Rate of return if state occurs Stokk SSS Recession 0.4 4% Boom 0.6 18% Consider following information. a) Calculate the expected return of a stock. b) Calculate...
-
When an electric field is applied to a shallow bath of vegetable oil, why do tiny bits of thread floating in the oil align with the field like compasses in a magnetic field?
-
What methods can a systems analyst employ to verify vendor claims about a software package?
-
What are the linkages among DFDs, decision tables, and E-R diagrams?
-
Develop a context diagram and as many nested DFDs as you consider necessary to represent all the details of the training logistics system described in the following narrative. If you discover that...
-
On December 31, 2017, James, Inc., borrowed \(\$ 300,000\) on a six percent, 20 -year mortgage note payable. The note is to be repaid in equal semiannual installments of \(\$ 12,979\) (beginning July...
-
Atlantic, Inc., plans to issue \(\$ 700,000\) of nine percent bonds that will pay interest semiannually and mature in ten years. Assume that the effective interest is eight percent per year...
-
On December 31, 2017, Blair Company issued \(\$ 600,000\) of 20 -year, 11 percent bonds payable for \(\$ 554,861\), yielding an effective interest rate of 12 percent. Interest is payable semiannually...
Study smarter with the SolutionInn App