You are the project manager for a team of 7 developers, and you have decided to use
Question:
You are the project manager for a team of 7 developers, and you have decided to use XP because of the small size of the team and the type of the project. At the end of iteration 1, the following information has been collected for the total work done by each developer (Note: not every developer is full-time, as observed from the information below)
If 2-calendar-week iterations are used here, what is the project velocity? Assume there were no official holidays in iteration 1
You want to schedule iteration 2 from the work repository below. Using the project velocity from iteration 1, and assuming 1 long weekend (3-day weekend) in the next 2 weeks, which tasks will make it to iteration 2? Ignore actual assignment of the tasks to specific develop