You have just used the network planning model and found the expected critical path length is 30
Fantastic news! We've Found the answer you've been seeking!
Question:
You have just used the network planning model and found the expected critical path length is 30 days and the variance of the critical path is 25. The probability that the project will be completed between 27 and 33 days is equal to (2 decimal accuracy)