You have the following parameters for a stochastic manufacturing line: rb=10 parts per hour; T0=2.1 hours; and
Fantastic news! We've Found the answer you've been seeking!
Question:
You have the following parameters for a stochastic manufacturing line: rb=10 parts per hour; T0=2.1 hours; and WIP (or w)=80 parts. What should be the value of actual throughput (THActual) to say that the system is lean (or good)? Circle the correct answer and show your calculation to support your answer: