Zihle contracts with Bob’s Builders for the development of a swimming pool in her backyard. For the builders to get their building equipment into the backyard, it is required that Zihle opens the side gate to her property, which is locked by a key that she keeps.
It is agreed that construction will take place on 1 January 2023 for a week. On the 1st of January, Bob’s Builders arrives at 08h00 in the morning as agreed with Zihle. Upon ringing the doorbell, however, there is no answer and without her unlocking the side gate, they are unable to gain access to the backyard.
After several missed phone calls and waiting over an hour for her to arrive, Bob’s Builders leave and attend another construction site.
Advise, in detail, what type of breach, if any, has occurred in this instance.